Project Reference No. 08430AG2098The Department of Transportation will retain an engineering firm to provide supplementary construction inspection staff of approximately one (1) inspector, under the Department's Inspector-in-Charge, for construction inspection and documentation services on various S.R.'s for the inspection and documentation of Roadside Development Contracts.
The Department will establish an order of ranking of a minimum of three (3) firms for the purpose of negotiating an Engineering Agreement based on the Department's evaluation of the acceptable letters of interest received in response to this solicitation. The ranking will be established directly from the letters of interest. Technical proposals will not be requested prior to the establishment of the ranking.
The following factors, listed in order of importance, will be considered by the Department during the evaluation of the firms submitting letters of interest:
a. Review of resumes with emphasis on ability to perform the basic needs of the contract which are understanding and interpreting of current design criteria and do inspections of guide rail, concrete median barriers and impact attenuator installation; assisting construction permit applicants and inspection of drainage, curb, roadway widening and utility installations on state highways; and inspection of roadside development work done by contractors for brushing, herbicide applications, landscaping, mowing, revitalization, and tree and stump removal.
b. Understanding of Department's requirements, policies and specifications.
c. Past performance.
d. Number of NICET certified inspectors in each payroll classification.
The qualifications and experience required of the firm's inspectors will be established by the Department, and the qualifications of the firm's proposed employees will be reviewed and approved by the Department.
It is anticipated that the supplementary construction inspection staff for this assignment will consist of the following number of inspectors who meet the requirements for the following inspection classification:
No. of
Classification Inspectors Transportation Construction Insp. Super. (TCIS) 1 (1) (NICET Highway Construction Level 3 or equivalent) The number(s) in parenthesis above indicate the number of inspectors in each Classification that must meet at least one of the following requirements:
1. Be certified by the National Institute for Certification in Engineering Technologies (NICET) in the field of Transportation Engineering Technology, subfield of Highway Construction, or subfield of Highway Materials, at the Level required for the Inspection Classification.
2. Be registered as a Professional Engineer by the Commonwealth of Pennsylvania with the required highway experience specified for the Inspection Classification.
3. Be certified as an Engineer-in-Training by the Commonwealth of Pennsylvania with the required highway experience specified for the Inspection Classification.
4. Hold a Bachelor of Science Degree in Civil Engineering or a Bachelor of Science Degree in Civil Engineering Technology with the required highway experience specified for the Inspection Classification.
5. Hold an Associate Degree in Civil Engineering Technology with the required highway experience specified for the Inspection Classification.
The maximum reimbursement per hour of inspection for each Department Payroll Classification for calendar year of 1997:
Payroll Classification Maximum Straight Time
Reimbursement Per Hour
of Inspection (TCIS) $38.21 The maximum reimbursement per hour of inspection includes all costs for providing construction inspection services at the project site during the normal work week.
Maximum reimbursement per hour of inspection for subsequent calendar years, if applicable, will be established at the scope of work meeting.
The firm selected may be required to attend a pre-construction conference with the Department and the construction contractor for this project. Under the supervision and direction of the Department's Inspector, the selected firm will be required to keep records and document the construction work; prepare current and final estimates for payment to the construction contractor; assist the Department in obtaining compliance with the labor standards, safety and accident prevention, and equal opportunity provisions of the contract item. The firm selected will be required to provide one (1) Transportation Construction Inspection Supervisor who has the ability to inspect brushing, herbicide application, landscaping, mowing operations, revitalization, and tree and stump removal. This inspector must have the ability to identify dead and dying trees and do roadside restoration inspection and help with preparation of contract specifications and documents and obtain compliance with Work Zone Traffic Control specifications. Also, this person will help supervise the Roadside Development inspectors in each County office. The inspector supervisor may be required to perform other duties as required.
The firm selected will be required to supply the following equipment at no direct cost to the Department:
1 Transportable Cellular Phone 1 Telephone Pager Letters of interest for this project must include a letter, signed by the individuals you propose for the TCIS position, giving their approval to use their name in your letter of interest for this specific project.
The maximum number of resumes to be included in the letter of interest shall be as follows:
Classification No. of Resumes TCIS 2 The second copy of the letter of interest and required forms, (see general requirements and information section) shall be sent to: Mr. Andrew Warren, District Administrator, 200 Radnor-Chester Road, St. Davids, PA 19087.
Any technical questions concerning the requirements for this project should be directed to Mr. Charles Stone, P.E., District 6-0, at (610) 964-6520.
Any questions concerning the submittal of the letter of interest can be directed to the Consultant Agreement Division at (717) 783-9309.
Montgomery County
Project Reference No. 08430AG2099The Department of Transportation will retain an engineering firm to provide supplementary construction inspection staff of approximately four (4) inspectors and two (2) Clerk Typists, under the Department's Inspector-in-Charge, for construction inspection and documentation services on various S.R.'s for the inspection and documentation of Highway Occupancy Permit Projects, and Roadside Development Contracts and other general maintenance contracts.
The Department will establish an order of ranking of a minimum of three (3) firms for the purpose of negotiating an Engineering Agreement based on the Department's evaluation of the acceptable letters of interest received in response to this solicitation. The ranking will be established directly from the letters of interest. Technical proposals will not be requested prior to the establishment of the ranking.
The following factors, listed in order of importance, will be considered by the Department during the evaluation of the firms submitting letters of interest:
a. Review of resumes with emphasis on ability to perform the basic needs of the contract which are understanding and interpreting of current design criteria and do inspections of guide rail, concrete median barriers and impact attenuator installation; assisting construction permit applicants and inspection of drainage, curb, roadway widening and utility installations on state highways; and inspection of roadside development work doe by contractors for brushing, herbicide applications, landscaping, mowing, revitalization, and tree and stump removal.
b. Understanding of Department's requirements, policies and specification.
c. Past performance.
d. Number of NICET certified inspectors in each payroll classification.
The qualifications and experience required of the firm's inspectors will be established by the Department, and the qualifications of the firm's proposed employees will be reviewed and approved by the Department.
It is anticipated that the supplementary construction inspection staff for this assignment will consist of the following number of inspectors who meet the requirements for the following inspection classifications:
No. of
Classification Inspectors Transportation Construction Inspector (TCI) 4 (3) (NICET Highway Construction Level 2 or equivalent) Clerk Typist II (CTII) 2 (0) The number(s) in parenthesis above indicate the number of inspectors in each Classification that must meet at least one of the following requirements:
1. Be certified by the National Institute for Certification in Engineering Technologies (NICET) in the field of Transportation Engineering Technology, subfield of Highway Construction, or subfield of Highway Materials, at the Level required for the Inspection Classification.
2. Be registered as a Professional Engineer by the Commonwealth of Pennsylvania with the required highway experience specified for the Inspection Classification.
3. Be certified as an Engineer-in-Training by the Commonwealth of Pennsylvania with the required highway experience specified for the Inspection Classification.
4. Hold a Bachelor of Science Degree in Civil Engineering or a Bachelor of Science Degree in Civil Engineering Technology with the required highway experience specified for the Inspection Classification.
5. Hold an Associate Degree in Civil Engineering Technology with the required highway experience specified for the Inspection Classification.
The maximum reimbursement per hour of inspection for each Department Payroll Classification for calendar year of 1997:
Payroll Classification Maximum Straight Time
Reimbursement Per Hour
of Inspection (TCI) $33.44 (CTII) $26.12 The maximum reimbursement per hour of inspection includes all costs for providing construction inspection services at the project site during the normal work week.
Maximum reimbursement per hour of inspection for subsequent calendar years, if applicable, will be established at the scope of work meeting.
The firm selected may be required to attend a pre-construction conference with the Department and the construction contractor for this project. Under the supervision and direction of the Department's Inspector, the selected firm will be required to keep records and document the construction work; prepare current and final estimates for payment to the construction contractor; assist the Department in obtaining compliance with the labor standards, safety and accident prevention, and equal opportunity provisions of the contract item. The firm selected will be required to provide two (2) Transportation Construction Inspectors for permit work who have the ability to perform the following: to conduct on-site inspection including all necessary information for evaluation, which includes but is not limited to sight distance, existing drainage, road condition, shoulder condition, grade of roadway and any additional condition which may require further study by the County Permit Engineer, Traffic Engineer, or Utility Engineer; assist applicant - private citizen, Township or Municipal authority and utility company by interpreting Pennsylvania Department of Transportation regulations on the driveway access, utility openings and method of restoration; attend municipal and utility preconstruction meetings to insure compliance with the Department of Transportation Regulations and coordination of inspection; enforce compliance with the Department of Transportation Publication 203 - Work Zone Traffic Control; inspect work being conducted by the permittee as well as insure restoration of occupancy area within our right-of-way; coordinate inspection efforts with the County Permit Inspector of the Maintenance Department in the County to insure permittee's compliance with regulations; maintain a diary of permits which require intensive study and follow up on violation; have sufficient physical stamina to work under adverse weather conditions and hazardous terrain and stress; appear as a witness if required by the Assistant District Attorney's office; perform the above duties and any other related work assignment that requires the same knowledge that a permit inspector has as directed or assigned by the County Maintenance Manager.
One (1) Transportation Construction Inspector must have the ability to inspect brushing, herbicide application, landscaping, mowing operations, revitalization, and tree and stump removal. This inspector must have the ability to identify dead and dying trees and do roadside restoration inspection and help with preparation of contract specifications and documents and obtain compliance with Work Zone Traffic Control specifications. One (1) Transportation Construction Inspector must be familiar with PennDOT guide rail construction specifications, and be able to prepare estimates and work orders, and obtain compliance with Work Zone Traffic Control specifications. All inspectors may be required to perform other duties as required.
The two (2) Clerk Typist II's will be required to type special Hauling permits, maintain route and detour book, maintain files on reimbursable inspection, log permit applications and perform other administrative duties. All Clerk Typist II's may be required to perform other duties as required.
The firm selected will be required to supply the following equipment at no direct cost to the Department:
1 Transportable Cellular Phone 6 Telephone Pagers 1 Polaroid Spectra II Camera 3 5-Power Abney Levels with Stadia The maximum number of resumes to be included in the letter of interest shall be as follows:
Classification No. of Resumes TCI 5 CTII 3 The second copy of the letter of interest and required forms, (see general requirements and information section) shall be sent to: Mr. Andrew Warren, District Administrator, 200 Radnor-Chester Road, St. Davids, PA 19087.
Any technical questions concerning the requirements for this project should be directed to Mr. Charles Stone, P.E., District 6-0, at (610) 964-6520.
Any questions concerning the submittal of the letter of interest can be directed to the Consultant Agreement Division at (717) 783-9309.
GENERAL REQUIREMENTS AND INFORMATION Firms interested in providing the above work and services are invited to submit two copies of a Letter of Interest and required information for each Project Reference Number for which the applicant wishes to be considered.
The first copy of the Letter of Interest and required information must be submitted to:
Mr. Charles W. Allwein, P.E., Chief
Consultant Selection Committee
7th Floor, Forum Place,
555 Walnut Street
Harrisburg, Pennsylvania 17101-1900The Letter of Interest and required information must be received within thirteen (13) calendar days of this Notice. The Deadline for receipt of a Letter of Interest at the above address is 4:30 P.M. prevailing time of the thirteenth day.
The second copy of the letter of interest and required information must be submitted to the appropriate District Engineer/Administrator or the Bureau Director as indicated in the individual advertisement. This copy must be postmarked or delivered on or before the deadline indicated above.
If an individual, firm, or corporation not authorized to engage in the practice of engineering desires to submit a Letter of Interest, said individual, firm, or corporation may do so as part of a Joint Venture with an individual, firm, or corporate which is permitted under the state law to engage in the practice of engineering.
If a Joint Venture responds to a project advertisement, the Department of Transportation will not accept separate Letters of Interest from the Joint Venture constituents. A firm will not be permitted to submit on more than one (1) Joint Venture for the same Project Reference Number. Also a firm that responds to a project as a prime may not be included as a designated subcontractor to another firm that responds as a prime to the project. Multiple responses under any of the foregoing situations will cause the rejection of all responses of the firm or firms involved. The above does not preclude a firm from being set forth as a designated subcontractor to more than one (1) prime responding to the project advertisement.
If a goal for Disadvantaged Business Enterprise (DBE) participation is established for an advertised project, firms expressing interest in the project must agree to ensure that Disadvantaged Business Enterprise (DBE) firms as defined in the Intermodal Surface Transportation Efficiency Act of 1991 and currently certified by the Department of Transportation shall have the maximum opportunity to participate in any subcontracting or furnishing supplies or services approved under Form 442, Section 1.10(a). The Act requires that firms owned and controlled by women (WBEs) be included, as a presumptive group, within the definition of Disadvantaged Business Enterprise (DBE). The goal for DBE participation shall be as stated in the individual project advertisement. Responding firms shall make good faith efforts to meet the DBE goal using DBEs (as they were defined prior to the act), WBEs or combinations thereof.
Proposing DBE firms must be certified at the time of submission of the Letter of Interest. If the selected firm fails to meet the established DBE participation goal, it shall be required to demonstrate its good faith efforts to attain the goal.
Responses are encouraged by small firms, Disadvantaged Business Enterprise (DBE) firms, and other firms who have not previously performed work for the Department of Transportation.
Each Letter of Interest must include the following information and the information must be packaged and presented in the following order:
1. Transmittal Letter (Maximum of two (2) typed pages, one side)
The subject heading of the transmittal letter must include the project reference number for which the applicant wishes to be considered, the firm's legal name, fictitious name (if applicable), and the firm's federal identification number. If the project advertisement indicated the Department will retain an engineering firm for the project, the applicant must indicate in the body of their transmittal letter the names and Professional engineer License Number of individuals who are directing heads or employees of the firm who have responsible charge of the firm's engineering activities, and whose names and seals shall be stamped on all plans, specifications, plats, and reports issued by the firm.
2. Project Organization Chart (one page, one side)
This Chart should show key staff from the prime and each subconsultant and their area of responsibility.
3. Standard Form 255, ''Architect-Engineer and Related Services Questionnaire for Specific Project'' (one Form 255 for the project team).
The Standard Form 255 must be signed, dated, and filled out in its entirety, including Item No. 6 listing the proposed subconsultants and the type of work or service they will perform on the project. Under Item 4 of this form, Column A should include the number of subconsultant personnel and Column B should include the number of prime consultant personnel to be assigned to work on this project reference number.
If a Disadvantage Business Enterprise (DBE) goal is specified for the project, the DBE must be currently certified by the Department of Transportation, and the name of the DBE and the work to be performed must be indicated in Item No. 6. If a Woman Business Enterprise (WBE) firm is substituted for the DBE, the WBE firm must also be presently certified by the Department of Transportation and indicated in Item 6.
4. Standard Form 254, ''Architect-Engineer for Related Services Questionnaire''
A Standard Form 254, not more than one (1) year old as of the date of this advertisement, must accompany each Letter of Interest for the firm, each party to a Joint Venture, and for each subconsultant the firm or Joint Venture is proposing to use for the performance of professional services regardless of whether the subconsultant is an individual, a college professor, or a Company, unless an acceptable Standard Form 254 for the prime and each subconsultant/subcontractor is on file in both the Bureau of Design and the Engineering District Office or Central Office Bureau identified in the individual project advertisement.
If the Standard Form 254 is not submitted with the Letter of Interest, the transmittal letter shall indicate the dates that the Standard Forms 254 were submitted to the Bureau of Design and appropriate Engineering District/Central Office Bureau.
These Forms shall be assembled with the prime's first, followed by the subconsultant's in the same order as they appear in Item 6 of Form 255.
5. Workload Projection Graph (Not required for Construction Inspection Services)
A Workload Projection Graph for the prime and each subconsultant should indicate the firm's current and anticipated workload compared to the anticipated capacity available for the next two-year time frame. The Workload Projection Graph should be submitted for the office(s) where the work would be performed and should only include the personnel classifications required for providing the advertised services and work.
6. Authorization Letters (if required)
If the advertisement requires a letter signed by individuals giving their approval to use their name in the Letter of Interest, the letters from proposed prime employees should be first, followed by subconsultant employees, in the same order as shown in Item 6 of Form 255.
7. Registration To Do Business
Firms with out-of-state headquarters or corporations not incorporated in Pennsylvania must include, with each Letter of Interest, a copy of their registration to do business in the Commonwealth as provided by the Department of State. Firms who are not registered to do business in Pennsylvania at the time of this advertisement must document that they have applied for registration to the Department of State, Corporation Bureau. The telephone number for the Corporation Bureau is (717) 787-1057 or (717) 787-2004.
8. Overhead Rates (one page)
This page must show the latest audited overhead rate developed in accordance with Federal Acquisition Regulations (FAR) for the prime consultant and each subconsultant. If a FAR rate is not available, the latest rate available from a Certified Public Account must be indicated. New firms should indicate how long the firm has been in existence and when an audited overhead rate would be available.
9. Additional Information
Additional information, not to exceed ten (10) one sided pages or five (5) double sided pages may be included at the discretion of the submitting firm.
The assignment of the agreement/contract for the above advertisement(s) will be made to one of the firms who submitted an acceptable Letter of Interest in response to the project advertisement. The assignment will be made based on the Department's evaluation of the firm's qualification and capabilities. The Department reserves the right to reject all letters submitted, to cancel the solicitations requested under this Notice, and/or to readvertise solicitation for the work and services.
BRADLEY L. MALLORY,
Secretary
[Pa.B. Doc. No. 97-1225. Filed for public inspection August 1, 1997, 9:00 a.m.]
No part of the information on this site may be reproduced for profit or sold for profit.This material has been drawn directly from the official Pennsylvania Bulletin full text database. Due to the limitations of HTML or differences in display capabilities of different browsers, this version may differ slightly from the official printed version.