   The Department plans to construct an 1,869.5 ft. steel deck truss, including approach spans over the Conrail Railroad and Lehigh River in Northampton County as part of the S. R. 33 Extension Section 001. The cost of the structure is estimated at a cost range of $20-$30 million. The contract anticipated bid opening date is March 1999 subject to FHWA Authorization. The Department is permitting a contractor designed concrete alternate bridge structure. Due to the cost and complexity of the bridge design and construction, the Department is making available preliminary design information.

   On request to PennDOT District 5-0 Bridge Unit, 1713 Lehigh Street, Allentown, Pennsylvania 18103-4727, (610) 798-4142, bidders may secure copies of the Type Size and Location Report, Foundation Recommendation Report and preliminary unofficial version of the Alternate Bridge Special Provision Part B. The cost for a single copy of this information is $100.00. Remittance for the Type Size and Location Report, Foundation Recommendation Report and preliminary unofficial version of the Alternate Bridge Special Provision Part B are to be made payable to the Pennsylvania Department of Transportation and must accompany your request. The information supplied by the Department or its authorized agents is of a preliminary nature and has been developed for the exclusive use of the Department to aid in the project design. Do not consider any of the data supplied or made available to you by the Department or its authorized agent as positive, representations of any of the conditions existing in the field. This information is not a part of the plans, proposal, or contract and is not to be considered a basis for computation of the unit prices used for bidding purposes. No claims will be considered based on any information in Type Size and Location Report, Foundation Recommendation Report and preliminary unofficial version of the Alternate Bridge Special Provision Part B. No refund for Type Size and Location Report, Foundation Recommendation Report and preliminary unofficial version of the Alternate Bridge Special Provision Part B will be made by the Department.

BRADLEY L. MALLORY,   
Secretary

[Pa.B. Doc. No. 98-1570. Filed for public inspection September 25, 1998, 9:00 a.m.]