NOTICES
TURNPIKE COMMISSION
Retention of an Engineering Firm
[31 Pa.B. 901]
Modification and Expansion of the Harrisburg East Interchange Dauphin County, PA
Reference No. 3-136 The Turnpike Commission (Commission) will retain an engineering firm to prepare preliminary and final design plans for the modification and expansion of the Harrisburg East Interchange (#19) Toll Plaza (Milepost 247.4) to provide an expanded facility for access to and from S.R. 283, in Lower Swatara Township, Dauphin County, Pennsylvania.
The required engineering services will include field surveys, coordination with utility companies and services, soils investigations, and corresponding reports. Architectural services will include design of the toll plaza building, interior design, landscape design, toll booths, canopy and other related tasks necessary for the Project. Significant building program data will be provided from previous similar Projects. In addition, the necessary plans and contract documents will be required for interchange signing, lighting, maintenance and protection of traffic, construction staging, contour grading, drainage, and roadside development. E-ZPass operations will be maintained during the construction of the new facility. Additional right-of-way is not anticipated as part of this Project. If environmental services are needed for this Project, they will be provided by others.
The following factors will be considered by the Commission during the evaluation of the firms submitting Letters of Interest for this project:
a. Specialized experience and technical competence of prime consultant and subconsultants. The Team must clearly demonstrate an ability to analyze available data to make decisions and develop plans to complete the project in a timely and cost effective manner.
b. Past record of performance with respect to cost control, work quality ability to meet schedules and previous experience on similar projects. The consultant should identify similar projects that have been completed by that firm as the prime, the magnitude of the project, and the client.
c. The specific experience and number of individuals who constitute the firm.
d. Location of consultant's office where the work will be performed.
e. Workload of the prime consultant and subconsultants for all Department of Transportation (Department) and Commission projects.
f. Other factors, if any, specific to the project.
Address these items and any necessary further details in a brief yet comprehensive manner in the letter of interest.
Direct inquires to Jeffrey C. Davis, P.E., (717) 939-9551, extension 5160 or by email to jdavis@paturnpike.com.
General Requirements and Information Firms interested in providing the above work and services are invited to submit a Letter of Interest with the required information. The Letters of Interest must include the following:
1. One page transmittal letter clearly identifying the project reference number, brief description of the project from the advertisement, the firm's federal identification number, the firm's legal name, contact person or project manager, address of corporate office and project office. (If the firm has multiple offices, the location of the office performing the work must be identified)
2. A three page expression of interest on the advertised project. Each firm should demonstrate their ability to perform the specific requirements indicated for the project and provide explanation that the firm has successfully completed similar type projects of the same magnitude.
3. An organization chart for the Project, identifying key personnel and any subconsultants and their roles. Any deviation from the subconsultant's listed in the letter of interest will require written approval from the Commission.
4. Tabulation of workload for the prime consultant and all subconsultants for all Department and Commission projects.
5. An Annual Qualification Package similar to the one submitted to the Department for the current year that is in the same District as the project or one that is best suited for the project.
The Annual Qualification Package should contain at a minimum the following information for the prime consultant and all subconsultants and attached to the back of the letter of interest (subs to follow primes):
* Standard Form (SF) 254--Architect-Engineer and Related Services Questionnaire in is entirety, not more than 1 year old as of the date of the advertisement.
* Resumes of key personnel expected to be involved in the project. (limit to one 8 1/2 x 11 page, one side, per person). Only resumes of key personnel should be included.
* Copy of the firm's registration to do business in the Commonwealth as provided by the Department of State for firms with out-of-state headquarters or corporations not incorporated in this Commonwealth.
* A copy of the Department's DBE/WBE Certification, if applicable.
If a Joint Venture responds to a project advertisement, the Commission will not accept separate letters of interest from joint venture constituents. A firm will not be permitted to submit a letter of interest on more than one joint venture for the same project reference number. Also, a firm that responds to a project as a prime may not be included as a designated subconsultant to another firm that responds to the same project advertisement. This does not preclude a firm from being set forth as a designated subconsultant to more than one prime consultant responding to the project advertisement.
The Commission is committed to the inclusion of disadvantaged, minority, and women firms in contracting opportunities. The minimum participation level for DBE/MBE/WBEs in these contracts will be 10% each. Responding firms will clearly identify DBE/MBE/WBE firms, expected to participate in these contracts, in their letter of interest. If the selected firm does not meet the minimum requirement for DBE/MBE/WBE participation, they will be required to demonstrate good faith efforts to acheive the required level. Proposed DBE/MBE/WBE firms must be certified by the Department of Transportation at the time of the submission of the letter of interest. If further information is desired concerning DBE/MBE/WBE participation, direct inquiries to the Office of Equal Opportunity Developement, Turnpike Commission, (717) 939-9551 ext. 4241.
Firms interested in performing the above services are invited to submit a letter of interest and required information to Barry L. Troup, P.E., Assistant Chief Engineer for Design, Turnpike Commission Administration Building, 176 Kost Road, Carlisle, PA 17013-0779. (FedEx address: 176 Kost Road, Carlisle, PA 17013-0779) (Mailing Address: P. O. Box 67676, Harrisburg, PA 17106-7676).
The letter of interest and required information must be received by 12 p.m., Friday, March 2, 2001. Any letters of interest received after this date and time will be time-stamped and returned.
Based on an evaluation of acceptable letters of interest received in response to these solicitations, one firm will be selected for each project. The order of preference will be established for the purpose of negotiating an agreement with the highest ranked firm established by the Technical Review Committee and approved by the Commission. Technical Proposals will not be requested prior to selection.
The Commission reserves the right to reject all letters of interest, to cancel solicitation requested under this notice, and/or to readvertise solicitation for the work and services.
BRADLEY L. MALLORY,
Chairperson
[Pa.B. Doc. No. 01-259. Filed for public inspection February 9, 2001, 9:00 a.m.]
No part of the information on this site may be reproduced for profit or sold for profit.This material has been drawn directly from the official Pennsylvania Bulletin full text database. Due to the limitations of HTML or differences in display capabilities of different browsers, this version may differ slightly from the official printed version.