[35 Pa.B. 6001]
[Continued from previous Web Page]
PUBLIC HEARINGS
Southcentral Region: Air Quality Program, 909 Elmerton Avenue, Harrisburg, PA 17110, Ronald Davis, New Source Review Chief, (717) 705-4702.
67-05083: Conectiv Mid-Merit LLC (P. O. Box 6066, 92 DC 72, Newark, DE 19714-6066) for construction of a combined cycle electric generating facility. The facility is in Peach Bottom Township, York County, off Atom Road along Pikes Peak Road, approximately 1 mile northeast of the Borough of Delta.
The proposed facility will have an overall nominal maximum generation capacity of 1,100 megawatts of electricity for sale. The primary fuel will be natural gas. Liquid distillate fuel (low sulfur light petroleum product or LSPP) will be used on a limited basis. The major components of the facility will include:
(a) Six nominal 100-megawatt Siemens Westinghouse V84.2 combustion turbines.
(b) Six selective catalytic reduction systems for NOx control.
(c) Six unfired heat recovery steam generators (HRSGs).
(d) Two nominal 150 MW steam turbines for a three-on-one configuration.
(e) Two 4 million gallon fuel oil tanks.
(f) Two mechanical draft cooling towers.
(g) Each turbine has a 135 ft. simple cycle stack and a 188 ft. combined cycle stack.
(h) Two 12,000-gallon (49,000 lb.) anhydrous ammonia tanks.
A modeling analysis was conducted for CO, NOx, SO2 and PM10. The modeling used five years of meterological data collected at the Peach Bottom nuclear facility and the New Castle County Airport in Wilmington, DE and the Environmental Protection Agency's approved AERMOD and CALPUFF models. The modeling indicated that none of the emissions from the turbines will have a significant impact on the surrounding area. Additional analyses were performed to assess the proposed facility's impact on soils, vegetation, and visibility in the area and the closest Class I area. The predicted impacts from all modeled pollutants fell within the allowable concentration levels as long as fuel oil firing is limited. A plan approval condition has been included to limit fuel oil firing to prevent visibility impacts at Class I areas.
Conectiv's emissions, along with additional background sources will consume the following portion of the available Prevention of Significant Deterioration air quality increments:
Pollutant Avg. Time Max. Modeled Impact
ug/m3Class II Area Increment
ug/m3PM10 24-hour 13.2 30 SO2 3-hour 60.0 512 SO2 24-hour 20.7 91 The plan approval includes the following limits on annual emission from the facility:
Pollutant Facility Total (tons/year) NOx 460.2 CO 439.3 PM/PM101 526.0 SO2 301.0 VOCs2 46.2 H2SO4 Mist 46.1 Ammonia 444.5 HAPs < 25 (total HAPs) < 10 (any single HAP) 1 Includes 5.3 tons/year (tpy) from cooling towers.
2 Includes 0.8 tpy from the liquid distillate fuel oil storage tanks, and 1.0 tpy form miscellaneous sources such as the pipeline gas condensate tank. The Plan approval will contain the following conditions to ensure compliance with the noted regulations:
General Plan Approval Requirements
1. This Plan Approval authorizes temporary operation of the sources covered by this Plan Approval provided the following conditions are met:
a. The Department must receive written notice from the permittee of the completion of construction and the Operator's intent to commence operation at least 5 working days prior to the completion of construction. The notice shall state when construction will be completed and when the permittee expects to commence operation.
b. Operation is authorized only to facilitate the start-up and shakedown of sources and air cleaning devices, to permit operations pending the issuance of an Operating Permit or to permit the evaluation of the sources for compliance with all applicable regulations and requirements.
c. This condition authorizes temporary operation of the sources for a period of 180 days from the date of commencement of operation, provided the Department receives notice from the permittee under Subpart (a).
d. The permittee may request an extension if compliance with all applicable regulations and Plan Approval requirements has not been established. The extension request shall be submitted in writing at least 15 days prior to the end of this period of temporary operation and shall provide a description of the compliance status of the source, a detailed schedule for establishing compliance and the reasons compliance has not been established. This temporary operation period will be valid for a limited time and may be extended for additional limited periods, each not to exceed 120 days.
2. This approval to construct shall become invalid if:
a. Construction (as defined in 40 CFR 52.21(b)(8)) has not commenced within 18 months of the issue date of this approval; or
b. Construction is discontinued for a period of 18 months or more.
Combustion Turbine Emission Restrictions
1. Under the Best Available Technology (BAT) provision of 25 Pa. Code § 127.1, the permittee shall limit the emission of ammonia from each SCR to:
10 ppmvd, volume corrected to 15% oxygen, 1 hour average; and
7 ppm, volume corrected to 15% oxygen on a daily average, both as measured by a certified continuous emissions monitor.
2. Under the BAT provision of 25 Pa. Code § 127.1, the permittee shall limit the emission of VOCs to 1.2 ppmvd, on an hourly basis volume corrected to 15% oxygen under normal operation for natural gas firing and to 1.3 ppmvd during gas firing in the diffusion mode and during oil firing. The VOCs are measured as methane.
3. The emission levels in Conditions 001, 002, 008 and 009 apply at all times except during periods of start-up and shutdown as defined as follows:
a. Start-up: Commences with the initiation of fuel injection into the combustion chambers and ends at the times specified as follows.
b. Cold Start-up: Refers to start-ups made more than 24 hours after shutdown. When operating in the simple cycle mode, a cold start-up shall not exceed 20 minutes. When operating in the combined cycle mode, a cold start-up shall not exceed 60 minutes.
c. Hot Start-up: Refers to start-ups made less than 24 hours after shutdown, and to mode changes and fuel switches. For mode changes and fuel switches, a hot start-up begins at the time the combustion turbine drops below 75% load. When operating in the simple cycle mode, a hot start-up shall not exceed 20 minutes. When operating in the combined cycle mode, a hot start-up shall not exceed 30 minutes.
d. Shutdown: Commences when the combustion turbine load falls below 75% and ends when the fuel injection into the combustion chambers is terminated. Shutdown periods shall not exceed 20 minutes per event.
4. The visible air contaminants from each combustion turbine exhaust stack shall not be emitted in a manner that the opacity of the emission is equal to or greater than 10% for a period or periods aggregating more than 3 minutes in any one hour; or equal to or greater than 30% at any time.
5. The operation of the turbines shall not result in malodorous emissions.
6. In accordance with the provisions of 25 Pa. Code Chapter 127, Subchapter E, New Source Review, the permittee shall secure Department-approved Emission Reduction Credits (ERCs) in the amount of 529 tons of NOx prior to the commencement of operation of the gas turbines.
7. Under the Lowest Achievable Emission Rate (LAER) provisions of 25 Pa. Code § 127.205, the Owner or Operator shall limit the NOx emissions (corrected to 15% O2) from each combustion turbine to the following
Startup Limits of NOx Emissions:
Simple Cycle Limits, lb/start Combined Cycle Limits, lb/start
Cold Start Hot Start Cold Start Hot Start Time, Min 20 20 60 30 Natural Gas 44 44 151 71 Fuel Oil 126 126 310 172
Shutdown Limits for NOx--20 minutes in duration
Fuel Gas LSLPP NOx Emissions, lb/shutdown 44 126 8. Under the LAER provisions of 25 Pa. Code § 127.205, the owner or operator shall limit the NOx emissions (corrected to 15% O2) from each combustion turbine to the following:
One-hour NOx averages calculated from a 3-hour rolling block average.
Mode Natural Gas Natural Gas or Liquid Fuel At 15% Oxygen Premix burner operation up to and including base load Peak Load* Diffusion mode operation up to including peak load* Simple Cycle 9 ppmvd 25 ppmvd 42 ppmvd Combined Cycle 2.5 ppmvd 5 ppmvd 8 ppmvd * Peak Operation is defined as any operating mode that requires a higher firing temperature than that required to achieve Base Operation ratings. The modes are uniquely defined by the unit control configuration and will be recorded by the owner or operator. 9. Under the Best Available Control Technology provisions of 25 Pa. Code § 127.83, the permittee shall limit the emissions from each combustion turbine to the following:
Combined Cycle Operations--Gas Firing
CO 6.0 ppmvd on an hourly basis (3-hour rolling average). SO2 0.0030 lb/mmBtu on an hourly basis. PM/PM10 0.0141 lb/mmBtu on an hourly basis. H2SO4 mist 0.00046 lb/mmBtu on an hourly basis. Combined Cycle Operations--Oil Firing
CO 6.0 ppmvd on an hourly basis (3-hour rolling average). SO2 0.051 lb/mmBtu on an hourly basis. PM/PM10 0.0287 lb/mmBtu (HHV) on an hourly basis. H2SO4 mist 0.0078 lb/mmBtu on an hourly basis. Simple Cycle Operations--Gas Firing
CO 6.0 ppmvd on an hourly basis (3-hour rolling average). SO2 0.0030 lb/mmBtu on an hourly basis. PM/PM10 0.0135 lb/mmBtu on an hourly basis. H2SO4 mist 0.00023 lb/mmBtu on an hourly basis. Simple Cycle Operations--Oil Firing
CO 6.0 ppmvd on an hourly basis (3-hour rolling average). SO2 0.051 lb/mmBtu on an hourly basis. PM/PM10 0.0184 lb/mmBtu on an hourly basis. H2SO4 mist 0.0039 lb/mmBtu on an hourly basis. All ppmvd values are based on dry measurements at 15% oxygen.
Combustion Turbine Fuel Restrictions
10. The natural gas burned in the combustion turbines shall not exceed 1.05 gr S/100 scf.
11. The maximum site daily turbine hours and fuel oil consumption in any 24-hour calendar day are limited to the following:
% S Turbine Hrs.
Peak LoadGallons Turbine Hrs
100% LoadGallons 0.05 40 449,600 43 483,320 0.03 55 618,200 58 651,920 0.02 67 753,080 71 798,040 0.01 84 944,160 91 1,022,840
The number of hours of liquid fuel firing (whether in combined cycle or simple cycle modes) shall not exceed 1,000 hours per CT on an annual basis. These annual operating hours may be totaled for all installed and operational units, up to six units, on a facility-wide basis (such as 6,000 hours of oil fired operation at the facility).
12. The liquid distillate fuel oil fired in the combustion turbines shall not exceed 0.05 weight percent sulfur.
13. Under the LAER provisions of 25 Pa. Code § 127.205, the permittee may use distillate oil in each combustion turbine while operating in the simple cycle mode when natural gas fuel is unavailable or if the unit is undergoing commissioning tests. Gas unavailability shall be defined as those periods of time when:
a. Physical damage, maintenance to pipelines or ancillary equipment prevents the delivery of gas to the turbines;
b. Equipment failure, maintenance or malfunction occurs so that gas pressures, temperatures or fuel quality are not adequate for turbine operation;
c. Unavailability due to physical limitation of supply at times of high pipeline demand, including insufficient pressures or flows; or
d. Electric Reliability Emergencies issued by PJM and supply of natural gas is inadequate.
Combustion Turbine Operating Hours Restriction
14. The permittee shall not operate the combustion turbines in the simple cycle mode except:
(1) During periods of unavailability of the combined cycle portion of the plant due to forced or planned maintenance outages during electrical emergencies of the PJM system;
(2) During periods when electric power produced by the combined cycle portion of the plant is undeliverable due to causes outside the control of the permittee during electrical emergencies of the PJM system; or
(3) As required for compliance, commissioning, optimization or PJM capacity testing.
An electrical emergency for the purpose of this condition is defined as one of the following:
a. A Maximum Emergency Generation Action has been issued by the PJM along with a Request to Purchase Emergency Power.
b. A Maximum Generation Alert has been issued by the PJM along with a Request to Purchase Emergency Power.
c. A local power emergency has occurred or is imminent.
15. Under the LAER provisions of 25 Pa. Code § 127.205, the permittee is authorized to operate each of the six combustion turbines in the following modes up to but not greater than the associated hourly limits:
Combined Cycle Mode
Fuel/Mode Turbine
LoadAnnual Operations Gas Premix Peak 100 hrs/yr Gas Premix 100% No Restriction Gas Diffusion Peak 200 hrs/yr Gas Diffusion 100% 200 hrs/yr Oil Firing Peak 100 hrs/yr Oil Firing 100% 900 hrs/yr Simple Cycle Mode
Fuel/Mode Turbine
LoadAnnual
OperationsGas Premix Peak 100 hrs/yr Gas Premix 100% Restricted by Condition 014 Oil Firing Peak Restricted by Conditions 011, 013 and 014 Oil Firing 100% Restricted by Conditions 011, 013 and 014 The Permittee shall not operate in diffusion mode (natural gas or oil) each of the six combustion turbines more than 200 hours during each NOx Budget Rule ''Control Period'' (as defined in 25 Pa. Code § 145.2). These hours of operation may be totaled for all installed and operational units, up to six units, on a facility-wide basis (that is 1,200 hours in diffusion gas and oil).
16. With respect to the operating periods specified in Condition 15, the permittee may operate the combustion turbines in diffusion mode during the NOx Budget Rule ''Control Period'' (as defined in 25 Pa. Code § 145.2) only when needed electric power output is not achievable through Premix mode of operation and one of the following conditions is met: (1) a Maximum Emergency Generation Action has been issued by the PJM Independent System Operator; or (2) a Maximum Generation Alert has been issued by the PJM along with a Request to Purchase Emergency Power; or (3) a local power emergency has occurred or is imminent; or (4) the PJM has directed the loading of a simple cycle combustion turbine that emits at higher NOx emissions rate than this facility operating in the diffusion mode.
The permittee shall maintain appropriate PJM notification and operating logs and records for a minimum of 5 years in order to verify compliance.
Within the 200 hours specified in Condition 15, the permittee may also operate in diffusion mode for emissions compliance testing, and/or PJM required capacity testing. The permittee may perform diffusion mode stack emissions compliance testing outside of the NOx Budget Rule ''Control Period.'' Should the Department require the permittee to perform diffusion mode emissions testing during this time period, any emissions testing hours will not be counted toward consumption of the 200-hour allotment.
For the local power emergency, the Department shall be notified by telephone within 24 hours (or the next business day whichever is greater) and a written description of the emergency shall be submitted to the Department within 7-business days.
This requirement does not apply during startup-up, shut down or during periods of operation upset when the unit automatically defaults to diffusion operation as indicated by the loss of the premix release signal. Any diffusion mode operation occurring during start-up, shut down or during periods of operation upset will be counted toward the consumption of the allotments as allowed under Condition 15.
Combustion Turbine Testing Requirements
17. Within 60 days after achieving the maximum firing rate, but not later than 180 days after start-up, the permittee shall demonstrate compliance with each of the emission limits established in Conditions 1, 2, 8 and 9 and opacity, as per 25 Pa. Code Chapter 139, 40 CFR Part 60 and Title IV. The applicant shall develop a testing protocol for HAP emissions and submit the protocol to the Department for review. The testing shall be conducted while the turbines are operating at or above 95% of full load for the ambient conditions at the time of the test.
18. Within 60 days after achieving the maximum firing rate, but no later than 180 days after startup, the permittee shall demonstrate compliance with the VOC emission limit established in Condition 2, as per 25 Pa. Code Chapter 139. The testing shall be done while the turbines are operating in two load ranges: 60 to 85% of maximum load and 85 to 100% of maximum load.
19. At least 60 days prior to the test, the permittee shall submit to the Department for approval, the procedures for the test and a sketch with dimensions indicating the location of sampling ports and other data to ensure the collection of representative samples.
20. At least 30 days prior to the test, the Regional Air Quality Program Manager shall be informed of the date and time of the test.
21. Within 45 days after the source tests, three copies of the complete test report, including all operating conditions, shall be submitted to the Regional Air Quality Program Manager for approval.
Combustion Turbine Monitoring Requirements
22. The permittee shall measure the following parameters for each SCR system:
a. Catalyst bed inlet gas temperature.
b. Ammonia injection rate.
23. Continuous emission monitoring (CEM) systems for NOx, CO and oxygen must be approved by the Department and installed, operated and maintained in accordance with the requirements of 25 Pa. Code Chapter 139 of the rules and regulations of the Department. Proposals containing information as listed in the Phase I section of the Department's ''Continuous Source Monitoring Manual'' for the CEMs must be submitted at least three months prior to start-up of the turbines.
Phase I Department approval must be obtained for the monitors above prior to initial startup of the source. Phase III Department approval must be obtained within 60 days of achieving the maximum production rate at which the source will be operated, but not later than 180 days after initial startup of the source. Department review time for the Phase III report (time between postmark of company's Phase III report and the postmark of the Department's response letter) will not be charged against the source in determining compliance with this condition. Information on obtaining Department approval is included in the Department's ''Continuous Source Monitoring Manual.''
NOx CEM must also comply with the requirements of 40 CFR 60.334(b) as required by Subpart GG Standards of Performance for Stationary Gas Turbines.
24. The permittee shall submit a plan for monitoring the ammonia slip from each SCR system for approval by the Department. This submittal shall be made in conjunction with those for the CEM system.
25. The permittee shall install and maintain fuel flow meters for all acid rain affected sources in accordance with the requirements of 40 CFR Part 75. The fuel flow will be measured in accordance with Part 75, Appendix D requirements, in lieu of stack exhaust flow monitoring, to allow for calculation of pollutant mass emission rates.
26. The permittee shall monitor the sulfur and nitrogen content of the fuel being fired in the combustion turbines as per 40 CFR 60.334(h). The frequency of monitoring the sulfur and nitrogen content as applicable shall be in accordance with 40 CFR 60.334(i).
Combustion Turbine Recordkeeping Requirements
27. Records required under this Plan Approval and 40 CFR Part 60 shall be kept for a period of 5 years and shall be made available to the Department upon its request.
a. The permittee shall maintain records of all air pollution control system performance evaluations and records of calibration checks, adjustments and maintenance performed on all equipment, which is subject to this plan approval.
b. The permittee shall maintain a copy of the manufacturer's recommendations for all the six combustion turbines and air pollution control equipment onsite.
c. The permittee shall maintain a copy of the manufacturer's recommendations for all CEMs that are required by this Plan Approval.
d. The permittee shall keep a record of the date of malfunctions, the time of the malfunction, the cause of the malfunction and the action taken to correct the malfunction.
28. The permittee shall record each start-up and shutdown, including date and times of each event. Emissions during start-up will be calculated based upon the emissions estimates approved by the Department and included in the total facility 12-month emissions.
29. The permittee shall, at a minimum, record the following:
a. Monthly fuel consumption rate and 12-month rolling total fuel consumption for each combustion turbine.
b. Hours of start-up and shutdown for each turbine.
c. Monthly hours of operation for each turbine in each mode.
30. Under the LAER provisions of 25 Pa. Code § 127.205, the permittee shall collect, record and maintain the documentation demonstrating the unavailability of natural gas leading to the usage of distillate fuel oil associated with Condition 13.
Combustion Turbine Additional Requirements
31. The Department reserves the right to use the CEMs data, stack test results, and the operating parameters determined during optimization of the turbines and their associated air cleaning devices to verify emission rates, to establish emission factors, and to develop compliance assurance measures in the Operating Permit.
32. The combustion turbine units are subject to the Title V Acid Rain Program of the Clean Air Act Amendments of 1990 and shall comply with all applicable provisions of that Title, to include the following:
40 CFR Part 72 Permits Regulation 40 CFR Part 73 SOx Allowance System 40 CFR Part 75 Continuous Emission Monitoring 40 CFR Part 77 Excess Emissions 33. The combustion turbines are subject to 40 CFR Part 60 Subpart GG of the Standards of Performance for New Stationary Sources. The equipment shall comply with all applicable requirements of the Subpart. 40 CFR 60.4 requires submission of copies of all requests, reports, applications, submittals, and other communications to both the EPA and the Department. The Environmental Protection Agency (EPA) copies shall be forwarded to the Director, Air Protection, U. S. EPA, Region III, 1650 Arch Street, Philadelphia, PA 19103-2029
Cooling Tower Emission Restrictions
1. The permittee shall limit particulate emissions from the source to 5.3 tons during any consecutive 12-month period.
2. The total solids concentration in the blowdown for each cooling tower shall not exceed 825 mg/l (averaged over a 12-month rolling period.)
3. The operation of the source shall not result in visible emissions, except uncombined water vapor.
Throughput Restrictions
4. The permittee shall limit the maximum water flow rate to the cooling towers to 145,200 gpm each (nominal).
Cooling Tower Monitoring Requirements
5. The permittee shall sample the cooling tower blowdown for total solids twice monthly as approved in the NPDES permit. Any changes to the sampling methods shall be submitted to the SCRO within 90 days of receiving approval from Water Quality.
6. The permittee shall at a minimum annually verify the accuracy of the flowmeters which are used to determine the flow of water entering the cooling towers. The results of the testing shall be submitted to the Department within 90 days.
Cooling Tower Recordkeeping Requirements
7. The permittee shall record the following:
a. Monthly average total solids in the cooling tower blowdown water.
b. Monthly volume of water entering the towers.
c. Monthly particulate emissions.
d. 12-month rolling total particulate emissions.
Cooling Tower Work Practice Requirements
No substances containing zinc or chromium shall be used in the water treatment chemicals for the cooling towers.
Tank Recordkeeping Requirements
The permittee shall maintain records of the following at a minimum:
1. Monthly fuel oil usage.
2. Monthly HAP and VOC emissions.
HAP and VOC emissions shall be included in the facility totals.
An appointment to review the pertinent documents at the Department of Environmental Protection, SouthcentralRegional Office, 909 Elmerton Avenue, Harrisburg PA 17110 may be scheduled by contacting the File Room at (717) 705-4732 between 8 a.m. and 3:30 p.m., Monday through Friday, except holidays.
A public hearing will be held for the purpose of receiving comments on the proposed action. The hearing will be held on December 7, 2005, at the Peach Bottom Recreation Center, 5 Pendyrus Street, Delta, PA at 7 p.m.
Those wishing to comment are requested to contact John Repetz at (717) 705-4904 at least 1 week in advance of the hearing to schedule their testimony. Commentators are requested to provide two written copies of their remarks at the time of the hearing. Oral testimony will be limited to a maximum of 10 minutes per individual. Organizations are requested to designate an individual to present testimony on behalf of the organization. Written comments may be submitted to Yasmin Neidlinger, Air Pollution Control Engineer, Department of Environmental Protection, 909 Elmerton Avenue, Harrisburg PA 17110 during the 30-day period following publication of this notice.
Persons with a disability who wish to attend the hearing scheduled for December 7, 2005, at 7 p.m. and who require an auxiliary aid, service or other accommodation to participate in the proceedings, should contact John Repetz directly at (717) 705-4904 or through the AT&T Relay Service at (800) 654-5984 (TDD) to discuss how the Department may accommodate their needs.
OPERATING PERMITS
Intent to Issue Title V Operating Permits under the Air Pollution Control Act (35 P. S. §§ 4001--4015) and 25 Pa. Code Chapter 127, Subchapter G.
Southcentral Region: Air Quality Program, 909 Elmerton Avenue, Harrisburg, PA 17110, Ronald Davis, New Source Review Chief, (717) 705-4702.
36-05136: Granger Energy of Honey Brook, LLC (481 South Churchtown Road, Narvon, PA 17555) for operation of a landfill gas treatment plant at their Lanchester Landfill in Caernarvon Township, Lancaster County. There are no potential emissions associated with the operation of this treatment plant. The treatment plant is subject to 40 CFR Part 60, Subpart WWW--Standards of Performance for Municipal Solid Waste Landfills. The Title V operating permit will include monitoring, recordkeeping, reporting and work practice requirements designed to keep the plant operating within all applicable air quality requirements.
Intent to Issue Operating Permits under the Air Pollution Control Act (35 P. S. §§ 4001--4015) and 25 Pa. Code Chapter 127, Subchapter F.
Southeast Region: Air Quality Program, 2 East Main Street, Norristown, PA 19428, Edward Jurdones Brown, Facilities Permitting Chief, (484) 250-5920.
09-00067: Rogers Foam Corp. (150 East Port Rd. Morrisville, PA 19428) for operation of various sources in Falls Township, Bucks County. The permit is for a non-Title V (State-only) facility. The major sources of air emissions are two adhesive spray booths, a glue station and a boiler. The permit will include monitoring, recordkeeping and reporting requirements designed to keep the facility operating within all applicable air quality requirements.
46-00250: Porter Instruments, Co. (235 Township Line Road, Hatfield, PA 19440) for operation of a precision dental, medical, and industrial application manufacturing facility in Upper Merion Township, Montgomery County. The permit is for a non-Title V (State-only) facility. The major source of air emissions is one batch vapor degreaser that uses 1,1,2-Trichloroethylene as its solvent. The permit will include monitoring, recordkeeping and reporting requirements designed to keep the facility operating within all applicable air quality requirements.
Southcentral Region: Air Quality Program, 909 Elmerton Avenue, Harrisburg, PA 17110, Ronald Davis, New Source Review Chief, (717) 705-4702.
06-03070: Atlas Minerals and Chemicals, Inc. (P. O. Box 38, Mertztown, PA 19539) for operation of a synthetic resins and specialty asphalts facility in Longswamp Township, Berks County. The State-only Operating Permit will include monitoring, recordkeeping, reporting requirements, emission restrictions and work practice standards designed to keep the facility operating within all applicable air quality requirements.
06-05091: Roeberg Enterprise, Inc. d/b/a Yorgey's Cleaners (1700 Fairview Street, Reading, PA 19606-2621) for operation of a petroleum based dry cleaning operation controlled by closed system cleaning machines in the City of Reading, Berks County. The facility is a non-Title V (State-only) facility. The facility will be required to limit the total emissions to less than the Title V thresholds during any consecutive 12-month period. The permit will include restrictions, work practices, monitoring, recordkeeping and reporting requirements designed to keep the facility within all air quality requirements.
22-03041: Librandi's Machine Shop, Inc. (93 Airport Drive HIA, Middletown, PA 17057) for electroplating operations including chromium electroplating controlled by surface tension method located in Middletown Borough, Dauphin County. The State-only operating permit shall contain additional monitoring, recordkeeping and operating restrictions designed to keep the facility operating within all applicable air quality requirements.
36-03005: Intelligencer Printing Co., Inc. (330 Eden Road, P. O. Box 1768, Lancaster, PA 17608) for an Operating Permit to operate their printing operation at their site in Manheim Township, Lancaster County. Emissions are estimated to be approximately 36.5 tons per year of VOCs. The State-only Operating Permit will contain additional recordkeeping and reporting requirements designed to keep the facility operating within all applicable air quality requirements.
Northcentral Region: Air Quality Program, 208 West Third Street, Williamsport, PA 17701, David Aldenderfer, Program Manager, (570) 327-3637.
49-00008: Milton Steel, Inc. (6 Canal Street, Milton, PA 17847) for operation of a steel shelving manufacturing facility in Milton Borough, Northumberland County.
The respective facility incorporates two heated paint dip tanks, a paint spray operation, various welding operations, 19 natural gas-fired heaters, furnaces, and the like, a solvent parts washer and a propane-fired emergency generator. The air contaminant emissions from this facility are not expected to exceed 32.05 tons of VOCs, 13.44 tons of hazardous air pollutants (of which no single hazardous air pollutant will total 10 or more tons per year), 4.51 tons of NOx, 3.18 tons of CO, 4.74 tons of particulate matter, all of which may be PM10 and .03 ton of SOx per year.
The facility is not a major (Title V) facility for any air contaminant but, due to the theoretical potential to emit both VOCs and hazardous air pollutants at levels which would qualify the facility as such, Milton Steel, Inc. has elected to restrict their ability to emit VOCs and hazardous air pollutants such that they will be a ''synthetic minor'' facility with respect to the Title V permitting requirements.
The Department of Environmental Protection (Department) proposes to incorporate into the operating permit to be issued conditions requiring compliance will all applicable regulatory requirements pertaining to air contamination sources and the emission of air contaminants as well as conditions previously established in Operating Permit 49-318-034. These previously-established conditions include conditions requiring both dip tanks to be operated indoors, to be equipped with lids that remain closed except when a tank is in actual use or during tank cleaning, to clean the coating circulation systems associated with the dip tanks by flushing solvent through the entire system and reclaiming as much of the solvent in liquid form as is practicable and to clean the dip tanks by draining as much coating mixture from the tanks as is practicable then allowing the remaining coating mixture to dry and physically removing the dried residue, a condition limiting the VOC content of the coating used in the ''blue tank'' to 3.3 pounds of VOCs per gallon of coating mixture averaged over each calendar month period taking into account all materials added to the tank during each respective month, a condition limiting the VOC content of the coating used in the ''orange tank'' to 3.1 pounds of VOC per gallon of coating mixture averaged over each calendar month taking into account all materials added to the tank during each respective month, a condition limiting the combined VOC emissions from the dip tanks to 30 tons in any 12-consecutive month period and the combined hazardous air pollutant emissions to 12 tons in any 12-consecutive month period, a condition prohibiting the use of coatings, coating additives and cleaning solvents which contain methylene chloride, 1,1,1-trichloroethane, perchloroethylene or formaldehyde and a condition requiring all volatile organic compound-containing materials to be stored in closed containers when not in actual use.
The Department additionally proposes to incorporate into the operating permit to be issued a condition limiting the total combined facility-wide emission of VOCs to less than 50 tons in any 12-consecutive month period and a condition limiting the total combined facility-wide emission of any single hazardous air pollutant to less than 10 tons in any 12-consecutive month period and the total combined facility-wide emission of all hazardous air pollutants combined to less than 25 tons in any 12-consecutive month period.
The Department also intends to incorporate into the operating permit to be issued appropriate recordkeeping and reporting requirements intended to help monitor compliance with the permit conditions described above as well as with applicable regulatory requirements.
Southwest Region: Air Quality Program, 400 Waterfront Drive, Pittsburgh, PA 15222-4745, Mark Wayner, Facilities Permitting Chief, (412) 442-4174.
03-00237: Rosebud Mining Co. (301 Market Street, Kittanning, PA 16201) to operate the coal processing, screening and loading operation at their Keystone East Mine in Plumcreek Township, Armstrong County.
Northwest Region: Air Quality Program, 230 Chestnut Street, Meadville, PA 16335-3481, Facilities Permitting Chief, (814) 332-6940.
42-00155: MSL Oil and Gas Corp. (Route 219 and Route 59 intersection, Lewis Run, Lafayette, PA 16738) for a Natural Minor Permit to operate a gas production and distribution corporation in Layfayette Township, McKean County. The significant sources are one compressor engine of 360 hp with dehydrator, one 186 hp compressor engine with catalytic converter, one 180 HP compressor engine, one 30,000 gallons propane tank and miscellaneous equipment leaks.
Department of Public Health, Air Management Services: 321 University Avenue, Philadelphia, PA 19104, Edward Braun, Chief, (215) 685-7584.
S01-001: The Purolite Co. (3620 G Street, Philadelphia, PA 19134) for operation of a ion exchange manufacturing facility in the City of Philadelphia, Philadelphia County. The facility's air emission sources include three No. 6 oil/No. 2 oil/ natural gas fired boilers each less than 10 mmBtu/hr, a polymerization process and a sulfonation process.
The operating permit will be issued under the 25 Pa. Code, Philadelphia Code Title 3 and Air Management Regulation XIII. Permit copies and other supporting information are available for public inspection at AMS, 321 University Avenue, Philadelphia, PA 19104. For further information, contact Edward Wiener at (215) 685-9426.
Persons wishing to file protest or comments on the operating permit must submit the protest or comments within 30 days from the date of this notice. Protests or comments filed with AMS must include a concise statement of the objections to the permit issuance and the relevant facts upon which the objections are based. Based upon the information received during the public comment period, AMS may modify the operating permit or schedule a public hearing. The hearing notice will be published in the Pennsylvania Bulletin and a local newspaper at least thirty days before the hearing.
COAL AND NONCOAL MINING ACTIVITY APPLICATIONS Applications under the Surface Mining Conservation and Reclamation Act (52 P. S. §§ 1396.1--1396.19a); the Noncoal Surface Mining Conservation and Reclamation Act (52 P. S. §§ 3301--3326); The Clean Streams Law (35 P. S. §§ 691.1--691.1001); the Coal Refuse Disposal Control Act (52 P. S. §§ 30.51--30.66); and The Bituminous Mine Subsidence and Land Conservation Act (52 P. S. §§ 1406.1--1406.21). Mining activity permits issued in response to applications will also address the applicable permitting requirements of the following statutes: the Air Pollution Control Act (35 P. S. §§ 4001--4015); the Dam Safety and Encroachments Act (32 P. S. §§ 693.1--693.27); and the Solid Waste Management Act (35 P. S. §§ 6018.101--6018.1003).
The following permit applications to conduct mining activities have been received by the Department of Environmental Protection (Department). A copy of an application is available for inspection at the district mining office indicated before an application. Where a 401 Water Quality Certification is needed for any aspect of a particular proposed mining activity, the submittal of the permit application will serve as the request for certification.
Written comments, objections or requests for informal conferences on applications may be submitted by any person or any officer or head of any Federal, State or local government agency or authority to the Department at the district mining office indicated before an application within 30 days of this publication, or within 30 days after the last publication of the applicant's newspaper advertisement, as provided by 25 Pa. Code §§ 77.121--77.123 and 86.31--86.34.
Where any of the mining activities listed will have discharges of wastewater to streams, the Department will incorporate NPDES permits into the mining activity permits issued in response to these applications. NPDES permits will contain, at a minimum, technology-based effluent limitations as identified in this notice for the respective coal and noncoal applications. In addition, more restrictive effluent limitations, restrictions on discharge volume or restrictions on the extent of mining which may occur will be incorporated into a mining activity permit, when necessary, for compliance with water quality standards (in accordance with 25 Pa. Code Chapters 93 and 95). Persons or agencies who have requested review of NPDES permit requirements for a particular mining activity within the previously mentioned public comment period will be provided with a 30-day period to review and submit comments on the requirements.
Written comments or objections should contain the name, address and telephone number of the person submitting comments or objections; the application number; and a statement of sufficient detail to inform the Department on the basis of comment or objection and relevant facts upon which it is based. Requests for an informal conference must contain the name, address and telephone number of requestor; the application number; a brief summary of the issues to be raised by the requestor at the conference; and a statement whether the requestor wishes to have the conference conducted in the locality of the proposed mining activities.
Coal Applications Received
Effluent Limits--The following coal mining applications that include an NPDES permit application will be subject to, at a minimum, the following technology-based effluent limitations for discharges of wastewater to streams:
30-Day Daily Instantaneous Parameter Average Maximum Maximum Iron (total) 3.0 mg/l 6.0 mg/l 7.0 mg/l Manganese (total) 2.0 mg/l 4.0 mg/l 5.0 mg/l Suspended solids 35 mg/l 70 mg/l 90 mg/l pH* greater than 6.0; less than 9.0
Alkalinity greater than acidity* * The parameter is applicable at all times.
A settleable solids instantaneous maximum limit of 0.5 ml/l applied to: (1) surface runoff (resulting from a precipitation event of less than or equal to a 10-year 24-hour event) from active mining areas, active areas disturbed by coal refuse disposal activities and mined areas backfilled and revegetated; and (2) drainage (resulting from a precipitation event of less than or equal to a 1-year 24-hour event) from coal refuse disposal piles.
California District Mining Office: 25 Technology Drive, Coal Center, PA 15423, (724) 769-1100.
32921601 and NPDES Permit No. PA0095117, Sprankle Mills Tipple (P. O. Box 343, Punxsutawney, PA 15767-0343), to revise the permit for the Valier Coal Yard in North Mahoning Township, Indiana County and related NPDES permit for coal stockpile, sediment trap and treatment basins. Surface Acres Proposed 1.2. Receiving stream: Crossman Run, classified for the following use: CWF. Application received July 15, 2005.
Cambria District Mining Office: 286 Industrial Park Road, Ebensburg, PA 15931, (814) 472-1900.
Permit No. 32990103 and NPDES No. PA0212687. TLH Coal Company, 4401 Pollock Road, Marion Center, PA 15759, permit renewal for reclamation only of a bituminous surface mine in Grant Township, Indiana County, affecting 30.1 acres. Receiving streams: UNTs to/and East Run, classified for the following uses: HQ-CWF. There are no potable water supply intakes within 10 miles downstream. Application received October 4, 2005.
56663098 and NPDES No. PA0607932. PBS Coals, Inc., P. O. Box 260, Friedens, PA 15541, permit renewal for the continued operation and restoration of a bituminous surface refuse reprocessing mine in Shade Township, Somerset County, affecting 412.3 acres. Receiving streams: Dark Shade Creek and Little Dark Shade Creek classified for the following use: CWF. There are no potable water supply intakes within 10 miles downstream. Application received September 27, 2005.
Permit No. 32010113 and NPDES Permit No. PA 0249106. TLH Coal Company Inc., 4401 Pollock Road, Marion Center, PA 15759, permit revision--land use change on Larry Ferringer property from cropland and forestland to unmanaged natural habitat in West Mahoning Township, Indiana County, affecting 21 acres. Receiving streams: UNTs to/and Mahoning Creek classified for the following use: WWF. There are no potable water supply intakes within 10 miles downstream. Application received on October 7, 2005.
Greensburg District Mining Office: R. R. 2, Box 603C, Greensburg, PA 15601, (724) 925-5500.
63940101 and NPDES Permit No. PA0200735. Robinson Coal Company (200 Neville Road, Neville Island, PA 15225). Revision application for land use change from forestland to pastureland to a bituminous surface mine, located in Robinson and Smith Townships, Washington County, affecting 160.4 acres. Receiving stream: UNT to Robinson Run, classified for the following use: WWF. There is no potable water supply intake within 10 miles downstream from the point of discharge. Revision application received: October 12, 2005.
Knox District Mining Office: White Memorial Building, P. O. Box 669, Best Avenue, Knox, PA 16232-0669, (814) 797-1191.
16000101 and NPDES Permit No. PA0241695. Milestone Crushed, Inc. (521 South Street, Clarion, PA 16214). Renewal of an existing bituminous surface strip and limestone and sandstone removal operation in Richland and Licking Townships, Clarion County affecting 83.6 acres. Receiving streams: UNTs to the Clarion River, classified for the following use: CWF. There are no potable surface water supply intakes within 10 miles downstream. Application received: October 6, 2005.
16000102 and NPDES Permit No. PA0241741. Milestone Crushed, Inc. (521 South Street, Clarion, PA 16214). Renewal of an existing bituminous surface strip operation in Perry Township, Clarion County affecting 38.6 acres. Receiving streams: UNT to Clarion River, classified for the following uses: CWF. There are no potable surface water supply intakes within 10 miles downstream. Application for reclamation only. Application received: October 12, 2005.
33000103 and NPDES Permit No. PA0241849. Falls Creek Energy Co., Inc. (R. D. 6, Box 231, Kittanning, PA 16201). Renewal of an existing bituminous surface strip and auger operation in McCalmont Township, Jefferson County affecting 57.1 acres. Receiving stream: Big Run to Mahoning Creek, classified for the following use: CWF. There are no potable surface water supply intakes within 10 miles downstream. Application for reclamation only. Application received: October 13, 2005.
16050111 and NPDES Permit No. PA0258041. Neiswonger Construction, Inc. (17592 Route 322, Strattanville, PA 16258). Commencement, operation and restoration of a bituminous surface strip operation in Porter Township, Clarion County affecting 86.0 acres. Receiving streams: UNT to Licking Creek to Clarion River and UNT to West Fork classified for the following uses: CWF. There are no potable surface water supply intakes within 10 miles downstream. Application received: October 12, 2005.
Moshannon District Mining Office: 186 Enterprise Dr, Phillipsburg, PA 16866, (814) 342-8200.
17020114 and NPDES No. PA0243361. Sky Haven Coal, Inc., 5510 State Park Road, Penfield, PA 15849, revision of an existing bituminous surface mine to remove the Lower Kittanning Nos. 2 and 3, and Lower Kitanning No. 4 coal seams from phase one mining plan and revise erosion and sedimentation control plans in Bradford Township, Clearfield County, affecting 85.7 acres. Receiving stream: Sulfur Run classified for the following use: CWF. Application received October 6, 2005.
07020902 and NPEDS No. PA0243345 Johnson Brothers Coal Company, Inc., 1390 Lee Run Road, Mahaffey, PA 15757, revision of an existing incidental coal mine to revise the mining area in Lawrence Township, Clearfield County, affecting 5.0 acres. Receiving stream: Laurel Run which is tributary to Little Clearfield Creek which is tributary to Clearfield Creek. Application received October 6, 2005.
Noncoal Applications Received
Effluent Limits
The following noncoal mining applications that include an NPDES permit application will be subject to, at a minimum, the following technology-based effluent limitations for discharges of wastewater to streams:
30-day Daily Instantaneous Parameter Average Maximum Maximum suspended solids 35 mg/l 70 mg/l 90 mg/l Alkalinity exceeding acidity1 pH1 greater than 6.0; less than 9.0 1 The parameter is applicable at all times.
A settleable solids instantaneous maximum limit of 0.5 ml/l applied to surface runoff resulting from a precipitation event of less than or equal to a 10-year 24-hour event. If coal will be extracted incidental to the extraction of noncoal minerals, at a minimum, the technology-based effluent limitations identified under coal applications will apply to discharges of wastewater to streams.
Moshannon District Mining Office: 186 Enterprise Drive, Phillipsburg, PA 16886, (814) 342-8200.
08050814. D. Terry and Tracy Kenney (P. O. Box 85, Wyalusing, PA 18853). Commencement, operation and restoration of a small industrial minerals (Flagstone) permit in Wilmot Township, Bradford County affecting 3.0 acres. Receiving streams: UNT to Susquehanna River. Application received: September 30, 2005.
FEDERAL WATER POLLUTION CONTROL ACT, SECTION 401 The following permit applications, requests for Environmental Assessment approval and requests for 401 Water Quality Certification have been received by the Department of Environmental Protection (Department). Section 401 of the Federal Water Pollution Control Act (FWPCA) (33 U.S.C.A. § 1341) requires the State to certify that the involved projects will not violate the applicable provisions of sections 301--303, 306 and 307 of the FWPCA (33 U.S.C.A. §§ 1311--1313, 1316 and 1317) as well as relevant State requirements. Persons objecting to approval of a request for certification under section 401 of the FWPCA or to the issuance of a Dam Permit, Water Obstruction and Encroachment Permit or the approval of an Environmental Assessment must submit comments, suggestions or objections within 30 days of the date of this notice, as well as questions, to the regional office noted before the application. Comments should contain the name, address and telephone number of the person commenting, identification of the certification request to which the comments or objections are addressed and a concise statement of comments, objections or suggestions including the relevant facts upon which they are based.
The Department may conduct a fact-finding hearing or an informal conference in response to comments if deemed necessary. Individuals will be notified, in writing, of the time and place of a scheduled hearing or conference concerning the certification request to which the comment, objection or suggestion relates. Maps, drawings and other data pertinent to the certification request are available for inspection between 8 a.m. and 4 p.m. on each working day at the regional office noted before the application.
Persons with a disability who wish to attend a hearing and require an auxiliary aid, service or other accommodation to participate in the proceedings should contact the specified program. TDD users should contact the Department through the Pennsylvania AT&T Relay Service at (800) 654-5984.
Applications received under the Dam Safety and Encroachments Act (32 P. S. §§ 693.1--693.27) and section 302 of the Flood Plain Management Act (32 P. S. § 679.302) and requests for certification under section 401(a) of the FWPCA (33 U.S.C.A. § 1341(a)).
WATER OBSTRUCTIONS AND ENCROACHMENTS Southeast Region: Water Management Program Manager, 2 East Main Street, Norristown, PA 19401.
E15-746. Department of Transportation, 7000 Geerdes Boulevard, King of Prussia, PA 19406, Thornbury Township, Chester County, ACOE Philadelphia District.
To remove, replace and maintain an existing 38-foot long, 16-foot wide and 6.5-foot high single span steel girder bridge located on Westtown-Thorndale Road (SR 2005, section 62B), with a single precast reinforced concrete ''ConSpan''-type arch measuring 48 feet long, 31-feet 7-inches wide and 12 feet high situated in and along a tributary to the East Branch of Chester Creek (WWF). Work will also include:
1. Approximately 212 feet and 158 feet of approach work on the north and south approaches, respectively.
2. Installation of stormwater facilities and associated outfall relocation along the north side of the proposed road downstream from the bridge.
3. Installation of the temporary access, consisting of causeways crossing the creek.
This site is located immediately after the SEPTA railroad underpass on Westtown-Thorndale Road (West Chester PA Quadrangle N: 6.4 inches; W: 6.4 inches). This application will replace existing application.
Northeast Region: Watershed Management Program Manager, 2 Public Square, Wilkes-Barre, PA 18711-0790, (570) 826-2511.
E39-453. Prospect Acquisitions, LP, 404 Sumneytown Pike, Suite 200, North Wales, PA 19454, in Upper Milford Township, Lehigh County, United States Army Corps of Engineers, Philadelphia District.
To construct and maintain an outfall to Leibert Creek (HQ-CWF) consisting of a 32-inch by 50-inch reinforced concrete eliptical pipe, and wall and riprap-lined outfall channel; a minor road crossing of PEM wetlands consisting of two 29-inch by 45-inch reinforced eliptical pipes and riprap apron; and two utility line crossings of wetlands. The encroachments are part of the Estates at Maple Ridge Residential Development located adjacent to Main Road West (SR 2023) approximately 0.5 mile west of the Pennsylvania Turnpike. (Allentown West, PA Quadrangle N: 0.3 inch; W: 1.2 inches).
E40-654. CAN DO, Inc., One South Church Street, 200 Renisance Center, Hazleton, PA 18201, in Hazle Township, Luzerne County, United States Army Corps of Engineers, Baltimore District.
To place fill or regrade within approximately 0.42 acre of PSS wetlands and several pond areas for the purpose of preparing a 75-acre site for industrial development. The project is known as the Harwood Inovation Site and is located on the east side of SR 081, approximately 0.5 mile south of SR 0924. (Conyngham, PA Quadrangle N: 11.0 inches; W: 2.0 inches).
E39-454. Principle Investment, LLC, 1611 Pond Road, Allentown, PA 18102, in Lower Macungie Township, Lehigh County, United States Army Corps of Engineers, Philadelphia District.
To construct and maintain two outfall structures in the floodway of the Little Lehigh Creek (HQ-CWF), the first consisting of an 18-inch RCP, concrete outlet structure and a cable concrete apron and the second consisting of a 24-inch RCP concrete outlet structure and a cable concrete apron. The outfalls are associated with the Olympic Ridge Residential Development located on the north side of Indian Creek Road (SR 2018) approximately 0.1 mile east of the Pennsylvania Turnpike. (Allentown West, PA Quadrangle N: 6.2 inches; W: 3.1 inches).
Southcentral Region: Water Management Program Manager, 909 Elmerton Avenue, Harrisburg, PA 17110.
E36-799: Townsedge Development, 48 South Market Street, Elizabethtown, PA 17022 in Conoy Township, Lancaster County, ACOE Baltimore District.
To construct and maintain a wetland enhancement project consisting of: wetland and floodplain grading; fill placement; and installation of tree and shrub plantings within 1.21 acres of farmed, palustrine emergent wetland associated with a UNT to Conoy Creek (TSF) located adjacent to the proposed Townsedge residential subdivision (York Haven, PA Quadrangle; Latitude: 40-05-51.30; Longitude: 76°40`13.09" in Conoy Township and Bainbridge Borough, Lancaster County. This project will result in 1.22 acres of functional floodplain Palustrine/Scrub-Shrub wetland.
E31-206: War Vets Field Project, 2401 Taylor Avenue, 2201 Moore Street, Huntingdon, PA 16652 in Huntingdon Borough, Huntingdon County, ACOE Baltimore District.
To construct a ticket booth, 6-feet wide by 30-foot 8-inches long, slab on grade one story block structure, located (Huntingdon, PA Quadrangle Latitude: 40°29`04", Longitude: 78°00`17") within the floodplain of the Juniata River (CWF-HQ) in the Borough of Huntingdon, Huntingdon County.
Northwest Region: Water Management Program Manager, 230 Chestnut Street, Meadville, PA 16335-3481.
E10-414. Bobbie Mikita, 501 Rollingridge Drive Suite 200, State College, PA 16801. Brookstone Residential Development, in Adams Township, Butler County, ACOE Pittsburgh District (Mars, PA Quadrangle N: 17.6 inches; W: 4.6 inches).
To fill 0.65 acre of Scrub-Shrub wetlands and 1,111 feet of a UNT to Breakneck Creek (WWF) during construction of the Brookstone Residential Subdivision along Forsythe Road located approximately 0.25 mile south of the intersection of Forsythe and Myoma Roads.
E25-041A. Erie Sand Steamship Company, P. O. Box 179, Erie, PA 16512-0179. Sand and Gravel Dredging in Lake Erie, ACOE Pittsburgh District.
The applicant has requested 5 year extension of Permit E25-041A to dredge sand and gravel ranging from 7 to 16 miles offshore of Presque Isle in Lake Erie under Sand and Gravel Agreement SG-001 at an area bounded by a point starting at 42°11.4`N, 80°17.2`W then 320°--3 miles, then 292°--3.16 miles, then 011°--4.15 miles, then 139°--5.18 miles, then 48°--1.61 miles, then 131°--2.3 miles, then 228°--1.84 miles, then 114°--1.44 miles, and then 236°--2.53 miles. Permit E25-041A expires on December 31, 2005, and is proposed to be extended to December 31, 2010.
ENVIRONMENTAL ASSESSMENTS Southcentral Region: Water Management Program Manager, 909 Elmerton Avenue, Harrisburg, PA 17110.
EA36-15: John S. Yost, 6059 Old Philadelphia Pike, Narvon, PA 17555 in Salisbury Township, Lancaster County, ACOE Baltimore District.
To install two grass waterways for stormwater management on a farm located at 6059 Old Philadelphia Pike in Salisbury Township, Lancaster County (Honey Brook USGS Quad, 40° 01` 57" N, 75° 57` 33" W). Construction of the waterways will involve approximately 3 acres of land disturbance, and the waterways will convey stormwater to a UNT of Pequea Creek (HQ-CWF).
EA36-16: Michael and Dawn Janssen, 1147 Holtwood Road, Holtwood, PA 17110 in East Drumore Township, Lancaster County, ACOE Baltimore District
To construct and maintain a 10-inch outfall pipe with a rip-rap rock apron which will discharge into the floodway of the Conowingo Creek (HQ-CWF) at a point located near the intersection of Cardinal Drive and Conowingo Drive (Wakefield, PA Quadrangle N: 17.0 inches; W: 10.0 inches) in East Drumore Township, Lancaster County.
DAM SAFETY Central Office: Bureau of Waterways Engineering, 400 Market Street, Floor 3, P. O. Box 8554, Harrisburg, PA 17105-8554.
D40-244. Wyoming Valley Inflatable Dam. Luzerne County Flood Protection Authority, Luzerne County Courthouse, 200 North River Street, Wilkes-Barre, PA 18711.
To construct, operate and maintain Wyoming Valley Inflatable Dam across the Susquehanna River (WWF), impacting 1.06 acres of wetlands (Palustrine Emergent and Palustrine Forested) and 4.5 miles of river, and providing 1.06 acres of wetland mitigation, for the purpose of revitalizing interest in the river through new recreation, scenic, and economic opportunities. Work includes construction of a 9.5-foot high 960-foot long inflatable run-of-the-river dam. (Wilkes-Barre West, PA Quadrangle N: 22.0 inches; W: 5.9 inches) in the City of Wilkes-Barre and Borough of Larksville, Luzerne County.
[Continued on next Web Page]
No part of the information on this site may be reproduced for profit or sold for profit.This material has been drawn directly from the official Pennsylvania Bulletin full text database. Due to the limitations of HTML or differences in display capabilities of different browsers, this version may differ slightly from the official printed version.