[50 Pa.B. 7028]
[Saturday, December 12, 2020]
[Continued from previous Web Page]
FEDERAL WATER POLLUTION CONTROL ACT SECTION 401 The following permit applications, requests for Environmental Assessment approval and requests for 401 Water Quality Certification have been received by the Department of Environmental Protection. Section 401 of the Federal Water Pollution Control Act (FWPCA) (33 U.S.C.A. § 1341), requires the State to certify that the involved projects will not violate the applicable provisions of Sections 301—303, 306 and 307 of the FWPCA (33 U.S.C.A. §§ 1311—1313, 1316 and 1317), as well as relevant state requirements. Persons objecting to approval of a request for certification under Section 401 or to the issuance of a Dam Permit or Water Obstruction and Encroachment Permit, or the approval of an Environmental Assessment must submit any comments, suggestions or objections within 30-days of the date of this notice, as well as any questions to the office noted above the application. Comments should contain the name, address and telephone number of the person commenting, identification of the certification request to which the comments or objections are addressed, and a concise statement of comments, objections or suggestions including the relevant facts upon which they are based.
The Department may conduct a fact-finding hearing or an informal conference in response to comments if deemed necessary. Each individual will be notified, in writing, of the time and place of a scheduled hearing or conference concerning the certification request to which the comment, objection or suggestion relates. Maps, drawings and other data pertinent to the certification request are available for inspection between the hours of 8:00 AM and 4:00 PM on each working day at the office noted above the application.
If you are a person with a disability and wish to attend the hearing and you require an auxiliary aid, service or other accommodation to participate in the proceedings, please contact the specified program. TDD users may contact the Department through the Pennsylvania AT&T Relay Service at (800) 654-5984.
WATER OBSTRUCTIONS AND ENCROACHMENTS
Applications Received Under the Dam Safety and Encroachments Act (32 P.S. §§ 693.1—693.27) and Section 302 of the Flood Plain Management Act (32 P.S. § 679.302) and Requests for Certification Under Section 401 of the Federal Water Pollution Control Act (33 U.S.C.A. § 1341(a)).
Southeast Region: Waterways & Wetlands Program Manager, 2 East Main Street, Norristown, PA 19401, Telephone 484-250-5160, E-mail: ra-epww-sero@pa.gov.
Permit No. E4601220-037, Pulte Group, Inc., 150 Allen Road, Suite 303, Basking Ridge, NJ 07920, Hatfield Township, Montgomery County, ACOE Philadelphia District.
To construct and maintain 160 single-family dwellings and 166-townhome units for age-qualified residential development and amenities within the floodway/floodplain of a UNT to Skippack Creek (TSF-MF), associated with the Del Webb North Penn Project. The project will also include the following activities:
1. Safely aligned intersection of Clemens and Forty Foot Roads at the entrance will require stream relocation, approximately 190-feet.
2. Internal roadway system will require approximately 85-feet stream impacts to a UNT to Skippack Creek.
3. Construct and maintain three outfall structures, two outlets into wetlands.
4. Construct and maintain four utility line stream crossings.
5. Minor road crossing at corner of northeastern property along the wetland (GP-7).
6. Temporary road crossing at northeastern property (GP-8).
7. Total stream length impact will be 275-feet and permanent wetland (PEM) impact will be 0.085 acre.
The site is located at 491 Forty Foot Road (Telford, PA USGS Quadrangles, Latitude: 40.265559; Longitude: -75.311706) in Hatfield Township, Montgomery County.
Northeast Region: Waterways & Wetlands Program, 2 Public Square, Wilkes-Barre, PA 18701-1915.
Contact: Gillian Ostrum, Clerk Typist 2, 570-830-3077.
E4502220-024. Tobyhanna Township, 105 Government Center Way, Pocono Pines, PA 18350, in Tobyhanna Township, Monroe County, U.S. Army Corps of Engineers, Philadelphia District.
To construct and maintain several road improvements near the I-380/SR940 interchange for the purpose of improving safety and traffic flow. The road improvements will permanently impact 0.90 acre of wetlands (EV) and cross a UNT to the Upper Tunkhannock Creek (HQ-CWF, MF) consisting of a 150-foot long, 18-inch HDPE pipe. To compensate for the permanent wetland impacts, the applicant will mitigate in a 2:1 ratio, providing 1.95 acres of new wetlands offsite. The project is located on the west side of the I-380/SR940 interchange (Pocono Pines, PA Quadrangle Latitude: 41° 6` 27" Longitude: -75° 24` 6") in Tobyhanna Township, Monroe County.
E3502220-023. Ramar Land Corporation, 600 Gillam Road, Wilmington, OH 45177, in Jermyn Borough, Lackawanna County, U.S. Army Corps of Engineers, Philadelphia District.
To permanently impact two PEM wetlands, totaling 0.09 acre, for the construction of a cross dock trucking facility, office, maintenance building and associated parking. The project is located at the intersection of S.R.107 Road and Bonnie Drive. (Carbondale, PA Quadrangle, Latitude: 41° 31` 42.25"; Longitude: -75° 32` 19.32").
Eastern Region: Oil and Gas Management Program Manager, 208 West Third Street, Suite 101, Williamsport, PA 17701-6448.
E5929220-030: Rockdale Marcellus, LLC, 4600 J. Barry Court, Suite 120, Canonsburg, PA 15317, Liberty Township, Tioga County, ACOE Baltimore District.
To construct, operate, and maintain:
1) A temporary road crossing using timber mats and a 16-inch diameter waterline impacting 1,744 square feet of an exceptional value palustrine emergent (EV-PEM) wetland (Liberty, PA Quadrangle 41° 35` 26" N, 77° 02` 15" W);
2) A temporary road crossing using timber mats and a 16-inch diameter waterline impacting 980 square feet of an exceptional value palustrine forested (EV-PFO) wetland (Liberty, PA Quadrangle 41° 35` 28" N, 77° 02` 08" W);
3) A temporary road crossing using timber mats and a 16 inch diameter waterline impacting 18 linear feet of an unnamed tributary to Salt Spring Run (HQ-CWF), 16 linear feet of another unnamed tributary to Salt Spring Run (HQ-CWF), and 668 square feet of an exceptional value palustrine forest (EV-PFO) wetland (Liberty, PA Quadrangle 41° 35` 29" N, 77° 02` 05" W);
The project will result in 34 linear feet of temporary stream impacts and 3,392 square feet (0.08 acre) of temporary wetland impacts all for the purpose of installing a freshwater pipeline in Liberty Township, Tioga County.
ENVIRONMENTAL ASSESSMENTS Southcentral Region: Waterways & Wetlands Program, 909 Elmerton Avenue, Harrisburg, PA 17110.
EA2103220-021. Upper Allen Township, 100 Gettysburg Pike, Mechanicsburg, PA 17055. Upper Allen Township, Cumberland County, U.S. Army Corps of Engineers Baltimore District.
The applicant proposes to restore and maintain 659 linear feet of an Unnamed Tributary to Yellow Breeches Creek (CWF, MF) by grading back high eroded stream banks to form stable banks and a stable floodplain bench, all within Spring Run Park in Upper Allen Township, Cumberland County (Latitude: 40.1717; Longitude: -76.9803).
EROSION AND SEDIMENT CONTROL The following parties have applied for an Erosion and Sediment Control Permit (ESCP) for an earth disturbance activity associated with either a road maintenance or timber harvesting operation.
Unless otherwise indicated, on the basis of preliminary review and application of lawful standards and regulations, the Department of Environmental Protection proposes to issue a permit to discharge, subject to certain limitations set forth in the permit conditions. These proposed determinations are tentative. Limitations are provided as erosion and sediment control best management practices (BMPs) which restrict the rate and quantity of sediment discharged.
Persons wishing to comment on the proposed permit are invited to submit a statement to the appropriate Department Regional Office listed above the application within 30-days of this public notice. Comments reviewed within this 30-day period will be considered in the formulation of the final determinations regarding this application. Responses should include the name, address, and telephone number of the writer and a concise statement to inform the Department of the exact basis of a comment and relevant facts upon which it is based. A public hearing may be held after consideration of comments received by the appropriate Department Regional Office during the 30-day public comment period.
Following the 30-day comment period, the appropriate Regional Office Water Management Program Manager will make a final determination regarding the proposed permit. Notice of this determination will be published in the Pennsylvania Bulletin at which time this determination may be appealed to the Environmental Hearing Board.
The application and related documents, including the erosion and sediment control plan for the earth disturbance activity are on file and may be inspected at the office identified in this notice.
Persons with a disability that require an auxiliary aid, service or other accommodation to participate during the 30-day public comment period should contact the specified Regional Office. TDD users may contact the Depart- ment through the Pennsylvania AT&T Relay Service at (800) 654-5984.
Applications received under Sections 5 and 402 of the Clean Streams Law (35 P.S. §§ 691.5 and 691.402).
Southwest Region: Oil and Gas Management Program Manager, 400 Waterfront Drive, Pittsburgh, PA 15222 (412) 442-4281.
E0407220-021: ETC Northeast Field Services, LLC, 6051 Wallace Road Extension, Suite 300, Wexford, PA 15090, Economy Borough, Beaver County, ACOE Pittsburgh District.
ETC Northeast Field Services, LLC is proposing to remediate a slope failure near Station 3+00 of the B15 Well Connect natural gas pipeline (40o 38` 23", -80o 10` 52"). The project requires permanent impacts to wetlands due to subsurface drains and reconstruction of the slope with engineered soil fill.
The project is located within the Baden USGS 7 1/2 Minute Quadrangle Map.
Resource
Permanent
Direct
Temporary
Direct
Temporary
Indirect
PEM (ac.) 0.021 0.03 ------ PSS (ac.) 0.008 0.15 0.018 Total 0.029 0.015 0.018 E0207220-038; ETC Northeast Pipeline, LLC, 6051 Wallace Road Extension, Third Floor, Wexford, PA 15090, Findlay Township, Allegheny County, Center, Conway, Independence, New Sewickley, Racoon Township(s), Beaver County, Jackson Township, Butler County, Robinson, Smith Townships, Washington County, ACOE Pittsburgh District.
The Revolution Pipeline project was originally permitted to install a 40.5-mile-long, 24-inch diameter steel natural gas pipeline that connects wells in Butler and Beaver counties to a natural gas processing facility in Washington County, Pennsylvania. This application is for the proposed restoration and on-site mitigation of aquatic resources impacted by the initial Revolution Pipeline construction, slope failures along the Revolution Pipeline ROW and the reconstruction of slope failures along the Revolution Pipeline ROW, the use of off-site mitigation for permanent impacts that cannot be restored on-site, unavoidable impacts to waters associated with landslide remediation and slope stabilization, and temporary impacts to waters for access for restoration and remediation activities.
The project is located within the Aliquippa, Baden, Beaver, Clinton, Evans City and Zelienople USGS 7 1/2 Minute Quadrangle Map.
See E0407220-023; E1007220-026 and E6307220-027 for additional impacts associated with this project.
Historic Impacts from the construction of the Revolution Pipeline include:
ALLEGHENY COUNTY (STA 1780+00 TO 1914+00) Stream 77-1 Ephemeral 40.481936 -80.347023 UNT to Potato Garden Run WWF Recovered, unauthorized impact by temporary access for pipeline installation. Temp 65 x 2 ft.
87 s.f.65 x 102 ft. 6,621 s.f. NA
Project Information PA DEP/105 Structure/
Activity Unique IdentifierAquatic Resource Type Latitude dd nad83 Longitude dd nad83 Waters Name PA Code Chapter 93 Designation Work
Proposed (1)DEP
Impact
Type Temp/
PermWatercourse Impact Linear foot (along channel) x Width (Top of Banks) Length and Width (feet) Floodway Impact Top of Bank Landward Length and Width (feet) Area
(square feet)Wetland
Impact
Length and
Width (feet)
Area
(square feet)PC-Stream 9-126 Ephemeral 40.479011 -80.346336 UNT to Potato Garden Run WWF Post-construction channel loss Perm 215 x 1 ft. 218 s.f. 215 x
101 ft. 21,715 s.f.NA PC-Stream 9-127 Ephemeral 40.477891 -80.344316 UNT to Potato Garden Run WWF Post-construction channel loss Temp 33 x 3 ft.
87 s.f.33 x 103 ft. 3,399 s.f. NA PC-Stream 11-33 Ephemeral 40.472977 -80.340128 UNT to Potato Garden Run WWF Post-construction channel loss Temp 68 x 4 ft. 261 s.f. 68 x 104 ft. 7,072 s.f. NA PC-Stream 13-4 Ephemeral 40.473126 -80.340152 UNT to Potato Garden Run WWF Post-construction channel loss Temp 97 x 1 ft.
87 s.f.97 x 101 ft. 9,797 s.f. NA PC-Wetland 13-A PEM 40.473099 -80.339948 NA NA Post-construction wetland loss Temp NA NA 29 x 26 ft.
392 s.f.Proposed Impacts:
ALLEGHENY COUNTY (STA 1780+00 TO 1914+00) GP-ACCESS-
Stream 77-1Ephemeral 40.481934 -80.347035 Trib 33757 to Potato Garden Run WWF GP-8 Temporary Equipment Access for Slope Stabilization Temp 26 x 1 ft.
26 s.f.100 x 57 ft. 5,700 s.f. NA Stream 9-127 Ephemeral 40.477837 -80.344343 UNT to Potato Garden Run WWF Grading w/in stream channel and floodway for restoration Temp 13 x 5 ft.
40 s.f.31 x 14 ft. 217 s.f. NA Stream 9-128 #3 Perennial 40.476953 -80.344278 Potato Garden Run WWF Slope Repair Temp 0 83 x 11 ft. 417 s.f. NA OUT-Stream 9-128 Perennial 40.476356 -80.343834 Potato Garden Run WWF Outfall Perm 0 4 x 8 ft.
32 s.f.NA Stream 9-128 #1 Perennial 40.476368 -80.343551 Potato Garden Run WWF Slope Repair Temp 100 x 12 ft. 1211 s.f. 160 x 30 ft. 5,180 s.f. NA
Project Information PA DEP/105 Structure/
Activity Unique IdentifierAquatic Resource Type Latitude dd nad83 Longitude dd nad83 Waters Name PA Code Chapter 93 Designation Work
Proposed(1)DEP Impact Type Temp/
PermWatercourse Impact Linear foot (along channel) x Width (Top of Banks) Length and Width (feet) Floodway Impact Top of Bank Landward Length and Width (feet) Area
(square feet)Wetland Impact
Length and
Width (feet)
Area
(square feet)Stream 9-128 #2 Perennial 40.476338 -80.343630 Potato Garden Run WWF Vegetated Riprap Perm 35 x 5 ft. 155 s.f. 95 x 10 ft. 916 s.f. NA GP-ACCESS-
Stream 9-128Perennial 40.476691 -80.344040 Potato Garden Run WWF GP-8 Temporary Equipment Access for Slope Stabilization Temp 48 x 20 ft. 819 s.f. 231 x 20 ft. 4,292 s.f. NA Wetland W-20200414-1417 CWI-A PEM 40.473019 -80.340172 NA NA Grading w/in wetland for restoration Temp NA NA 54 x 24 ft.
566 s.f.Stream 11-33 Ephemeral 40.472979 -80.340132 UNT to Potato Garden Run WWF Grading w/in stream channel and floodway for restoration Temp 22 x 4 ft.
86 s.f.14 x 6 ft.
41 s.f.NA Stream 13-4 Ephemeral 40.473128 -80.340158 UNT to Potato Garden Run WWF Grading w/in stream channel and floodway for restoration Temp 97 x 1 ft.
97 s.f.89 x 81 ft. 4,856 s.f. NA Stream 11-32 Perennial 40.473104 -80.339778 UNT to Potato Garden Run WWF Temporary Disturbance for Bank Stabilization and Pump Around Discharge Temp 62 x 12 ft. 531 s.f. 126 x 101 ft. 6,098 s.f. NA E407220-023; ETC Northeast Pipeline, LLC, 6051 Wallace Road Extension, Third Floor, Wexford, PA 15090, Findlay Township, Allegheny County, Center, Conway, Independence, New Sewickley, Racoon Township(s), Beaver County, Jackson Township, Butler County, Robinson, Smith Townships, Washington County, ACOE Pittsburgh District.
The Revolution Pipeline project was originally permitted to install a 40.5-mile-long, 24-inch diameter steel natural gas pipeline that connects wells in Butler and Beaver counties to a natural gas processing facility in Washington County, Pennsylvania. This application is for the proposed restoration and on-site mitigation of aquatic resources impacted by the initial Revolution Pipeline construction, slope failures along the Revolution Pipeline ROW and the reconstruction of slope failures along the Revolution Pipeline ROW, the use of off-site mitigation for permanent impacts that cannot be restored on-site, unavoidable impacts to waters associated with landslide remediation and slope stabilization, and temporary impacts to waters for access for restoration and remediation activities.
The project is located within the Aliquippa, Baden, Beaver, Clinton, Evans City and Zelienople USGS 7 1/2 Minute Quadrangle Map.
See E0207220-038; E1007220-026 and E6307220-027 for additional impacts associated with this project.
Historic Impacts from the construction of the Revolution Pipeline include:
BEAVER COUNTY (STA 254+00 TO 1780+00) PC-Wetland 10-G PSS 40.731001 -80.157909 NA NA Post-construction wetland loss Temp NA NA 258 x 41 ft.
6,186 s.f.PC-Wetland 1-A PSS 40.728771 -80.162082 NA NA Post-construction conversion PSS to PEM Temp NA NA 123 x 105 ft. 7,362 s.f. PC-Wetland 1-C PEM 40.728665 -80.162898 NA NA Post-construction wetland loss Temp NA NA 106 x 60 ft. 3,703 s.f. Wetland 9-CS PSS 40.726998 -80.162336 NA NA Recovered unauthorized impact by temporary access for pipeline installation Temp NA NA 4 x 3 ft.
6 s.f.
PROJECT INFORMATION PA DEP/105 Structure/
Activity Unique IdentifierAquatic Resource Type Latitude dd nad83 Longitude dd nad83 Waters Name PA Code Chapter 93 Designation Work
Proposed(1)DEP Impact Type Temp/
PermWatercourse Impact Linear foot (along channel) x Width (Top of Banks) Length and Width (feet) Floodway Impact Top of Bank Landward Length and Width (feet) Area
(square feet)Wetland Impact
Length and Width (feet) Area
(square feet)Stream 10-21 Intermittent 40.726625 -80.162118 UNT to Brush Creek WWF Recovered, unauthorized impact by pipeline installation. Temp 129 x 4 ft. 523 s.f. 129 x 104 ft. 13,416 s.f. NA Stream 1-2 Ephemeral 40.719211 -80.164326 UNT to Trib 34825 to Brush Creek WWF Recovered, unauthorized impact by temporary access for pipeline installation. Temp 24 x 13 ft. 305 s.f. 24 x 113 ft. 2,701 s.f. NA PC-Wetland 9-BZ PSS 40.717174 -80.162854 NA NA Post-construction conversion PSS to PEM Temp NA NA 73 x 36 ft.
2,265 s.f.PC-Wetland 9-BV PEM 40.708846 -80.170171 NA NA Post-construction conversion PFO to PEM Temp NA NA 160 x 39 ft.
3,746 s.f.PC-Wetland 9-CF PEM 40.704771 -80.172522 NA NA Post-construction conversion PFO to PEM Temp NA NA 261 x 42 ft.
4,008 s.f.Stream S-20200330-1307 JWR Intermittent 40.733559 -80.165878 UNT to Brush Creek WWF Recovered, unauthorized impact by pipeline installation. Temp 218 x 2 ft. 436 s.f. 218 x 102 ft. 22,216 s.f. NA Stream 11-59 Intermittent 40.690195 -80.178150 UNT to Trib 36572 to Crows Run WWF Recovered, unauthorized impact by temporary access for pipeline installation. Temp 37 x 4 ft. 131 s.f. 37 x 104ft. 3,833 s.f. NA PC-Stream 11-5 Ephemeral 40.691071 -80.183008 Tributary 36572 to Crows Run WWF Post-construction channel realignment Temp 85 x 2 ft. 131 s.f. 0 NA PC-Stream 11-7 Ephemeral 40.686910 -80.196349 UNT to Crows Run WWF Post-construction channel loss Temp 214 x 3 ft. 610 s.f. 214 x 103 ft. 22,042 s.f. NA PC-Wetland 13-C PSS 40.680166 -80.205459 NA NA Post-construction wetland loss Temp NA NA 236 x 77 ft.
8,407 s.f.PC-Stream 11-12 Perennial 40.680100 -80.205333 Pine Run WWF Post-construction streambank erosion. Temp 51 x 7 ft. 304 s.f. 0 NA PC-Stream 11-30 (Crows Run) Perennial 40.678996 -80.204938 Crows Run WWF Post-construction streambank erosion Temp 70 x 17 ft. 915 s.f. 0 NA PC-Stream 9-2-11 Intermittent 40.678428 -80.210620 UNT to Crows Run WWF Post-construction streambank erosion Temp 84 x 7 ft. 305 s.f. 0 NA PC-Stream 2-19 Perennial 40.676443 -80.229452 UNT to Crows Run WWF Post-construction streambank erosion Temp 105 x 6 ft. 479 s.f. 0 NA Wetland W-20200331-
1245-DWLPEM 40.676364 -80.229374 NA NA Recovered, unauthorized impact by temporary access for pipeline installation. Temp NA NA 25 x 12 ft.
174 s.f.PC-Wetland 2-N PEM 40.669472 -80.263507 NA NA Post-construction wetland loss Perm NA NA 88 x 15 ft.
740 s.f.PC-Stream 2-25 Intermittent 40.669403 -80.264577 UNT to Moon Run WWF Post-construction channel loss Perm 70 x 6 ft. 392 s.f. 70 x 106 ft. 7,420 s.f. NA
PROJECT INFORMATION PA DEP/105 Structure/
Activity Unique IdentifierAquatic Resource Type Latitude dd nad83 Longitude dd nad83 Waters Name PA Code Chapter 93 Designation Work
Proposd (1)DEP Impact Type Temp/
PermWatercourse Impact Linear foot (along channel) x Width (Top of Banks) Length and Width (feet) Floodway Impact Top of Bank Landward Length and Width (feet) Area
(square feet)Wetland Impact
Length and
Width (feet)
Area
(square feet)PC-Stream 2-24 (Elkhorn Run) Perennial 40.668800 -80.270300 Elkhorn Run WWF Post-construction channel loss Temp 249 x 22 ft. 5,489 s.f 249 x 122 ft. 30,378 s.f. NA PC-Wetland 2-F PEM 40.636074 -80.296698 NA NA Post-construction wetland loss Temp NA NA 52 x 29 ft. 1,220 s.f. PC-Wetland 2-R PEM 40.629177 -80.303213 NA NA Post-construction wetland loss Temp NA NA 72 x 56 ft. 1,655 s.f. Stream S-20200418-1236 JWR #1 Ephemeral 40.626305 -80.305526 UNT to Raccoon Creek WWF Recovered, unauthorized impact by temporary access for pipeline installation. Temp 35 x 4 ft. 131 s.f. 35 x 104 ft. 3,659 s.f. NA PC-Stream 9-138 Intermittent 40.624635 -80.306124 UNT to Raccoon Creek WWF Post-construction channel realignment Temp 91 x 2 ft. 182 s.f. 0 NA PC-Stream 9-137 Intermittent 40.624726 -80.306007 UNT to Raccoon Creek WWF Post-construction channel loss Temp 165 x 1 ft. 174 s.f. 165 x 101 ft. 16,683 s.f. NA PC-Stream 9-136 Perennial 40.624532 -80.305920 UNT to Raccoon Creek WWF Post-construction channel realignment Temp 20 x 10 ft. 21 s.f. 0 NA PC-Stream 9-140 Ephemeral 40.623196 -80.306646 UNT to Raccoon Creek WWF Post-construction channel loss Temp 149 x 6 ft. 915 s.f. 149 x 106 ft. 15,794 s.f. NA PC-Wetland 9-DY PEM 40.622649 -80.308614 NA NA Post-construction wetland loss Perm NA NA 70 x 50 ft. 2,004 s.f. PC-Wetland 9-DX PEM 40.622714 -80.308984 NA NA Post-construction wetland loss Perm NA NA 87 x 63 ft. 2,875 s.f. PC-Stream 9-143 Intermittent 40.622474 -80.309060 UNT to Raccoon Creek WWF Post-construction channel loss Perm 204 x 3 ft. 609 s.f. 204 x 103 ft. 20,996 s.f. NA PC-Stream 9-144 Intermittent 40.622506 -80.309004 UNT to Raccoon Creek WWF Post-construction channel loss Perm 64 x 3 ft. 174 s.f. 64 x 103 ft. 6,592 s.f. NA PC-Stream 9-142 Intermittent 40.622462 -80.309690 UNT to Raccoon Creek WWF Post-construction channel loss Perm 42 x 3 ft. 131 s.f. 42 x 103 ft. 4,312 s.f. NA PC-Wetland 10-I PEM 40.622368 -80.309715 NA NA Post-construction wetland loss Perm NA NA 45 x 32 ft.
1, 045 s.f.PC-Wetland 9-Y PEM 40.617308 -80.326493 NA NA Post-construction wetland loss Perm NA NA 137 x 34 ft.
1,873 s.f.PC-Stream 9-30 Intermittent 40.616590 -80.329428 UNT to Raccoon Creek WWF Post-construction channel loss Perm 107 x 2 ft. 218 s.f. 107 x 102 ft. 10,914 s.f. NA PC-Stream 9-31 Intermittent 40.616486 -80.329590 UNT to Raccoon Creek WWF Post-construction channel loss Perm 53 x 2 ft.
87 s.f.53 x 102 ft. 5,406 s.f. NA PC-Wetland 9-BI PEM 40.615705 -80.330794 NA NA Post-construction wetland loss Temp NA NA 71 x 27 ft. 1,481 s.f. PC-Wetland 9-AG (2-AG) PEM 40.611546 -80.329982 NA NA Post-construction wetland loss Temp NA NA 119 x 21 ft.
1,176 s.f.
PROJECT INFORMATION PA DEP/105 Structure/
Activity Unique IdentifierAquatic Resource Type Latitude dd nad83 Longitude dd nad83 Waters Name PA Code Chapter 93 Designation Work
Proposed (1)DEP Impact Type Temp/ Perm Watercourse Impact Linear foot (along channel) x Width (Top of Banks) Length and Width (feet) Floodway Impact Top of Bank Landward Length and Width (feet) Area
(square feet)Wetland Impact
Length and Width (feet)
Area
(square feet)PC-Wetland 9-DL PSS 40.606768 -80.327086 NA NA Post-construction wetland loss Perm NA NA 63 x 33 ft. 1,176 s.f. PC-Wetland 9-DN PSS 40.605880 -80.327434 NA NA Post-construction wetland loss Perm NA NA 42 x 31 ft.
915 s.f.PC-Stream 9-147 Intermittent 40.600528 -80.328684 UNT to Raccoon Creek WWF Post-construction channel loss Perm 114 x 2 ft. 218 s.f. 114 x 102 ft. 11,628 s.f. NA PC-Wetland 9-EC PSS 40.600427 -80.328844 NA NA Post-construction wetland loss Perm NA NA 93 x 46 ft. 3,049 s.f. PC-Wetland 9-EE PSS 40.600078 -80.328374 NA NA Post-construction wetland loss Perm NA NA 36 x 25 ft.
653 s.f.PC-Stream 9-64 Perennial 40.593352 -80.328337 UNT to Frames Run WWF Post-construction channel loss Perm 67 x 3 ft. 218 s.f. 67 x 103 ft. 6,901 s.f. NA PC-Stream 9-63 Perennial 40.593331 -80.328149 Frames Run WWF Post-construction channel fill, streambank erosion Temp 349 x 20 ft. 5,576 s.f. 0 NA PC-Stream 9-164 Ephemeral 40.584963 -80.333664 UNT to Tributary 33594 to Service Creek WWF Post-construction channel fill, streambank erosion Temp 108 x 15 ft. 1,612 s.f. 0 NA PC-Wetland 9-EP PEM 40.584595 -80.335935 NA NA Post-construction wetland loss Perm NA NA 59 x 23 ft. 1,089 s.f. PC-Wetland 9-EO PEM 40.579814 -80.337336 NA NA Post-construction wetland loss Temp NA NA 60 x 27 ft. 1,045 s.f. Wetland 23-A PEM 40.576754 -80.335983 NA Recovered, unauthorized impact by temporary access for pipeline installation. Temp NA NA 86 x 98 ft. 4,704 s.f. PC-Stream 9-151 Ephemeral 40.573228 -80.331823 UNT to Service Creek WWF Post-construction channel loss Temp 138 x 3 ft. 392 s.f. 138 x 103 ft. 14,214 s.f. NA PC-Stream 9-152 Perennial 40.573499 -80.331918 UNT to Service Creek WWF Post-construction channel fill, streambank erosion Temp 136 x 8 ft. 741 s.f. 0 NA PC-Wetland 9-EI PEM 40.561764 -80.330033 NA NA Post-construction wetland loss Temp NA NA 55 x 44 ft. 1,089 s.f. PC-Wetland 9-DF PEM 40.551541 -80.340636 NA NA Post-construction conversion PFO to PEM Temp NA NA 83 x 61 ft. 3,833 s.f. PC-Stream 2-35 Perennial 40.545240 -80.343379 UNT to Obney Run WWF Post-construction streambank erosion Temp 115 x 12 ft. 1,307 s.f. 0 NA PC-Wetland 13-AD PEM 40.544836 -80.343659 NA NA Post-construction wetland loss Perm NA NA 46 x 22 ft.
653 s.f.PC-Stream 9-109 (Stream 13-107B) Perennial 40.534831 -80.351350 UNT to Raccoon Creek WWF Post-construction streambank erosion Temp 153 x 4 ft. 871 s.f. 0 NA
PROJECT INFORMATION PA DEP/105 Structure/
Activity Unique IdentifierAquatic Resource Type Latitude dd nad83 Longitude dd nad83 Waters Name PA Code Chapter 93 Designation Work
Proposed(1)DEP Impact Type Temp/
PermWatercourse Impact Linear foot (along channel) x Width (Top of Banks) Length and Width (feet) Floodway Impact Top of Bank Landward Length and Width (feet) Area
(square feet)Wetland Impact Length and Width (feet) Area
(square feet)Wetland 42-D PEM 40.534747 -80.351206 NA NA Recovered, unauthorized impact by pipeline installation. Temp NA NA 29 x 2 ft.
58 s.fTemp NA NA 29 x 17 ft.
395 s.f.PC-Stream 9-36 Perennial 40.509578 -80.350945 UNT Raccoon Creek WWF Post-construction channel loss Temp 358 x 3 ft. 1,074 s.f. 358 x 103 ft. 36,874 s.f. NA PC-Wetland 9-AK PEM 40.508454 -80.350936 NA NA Post-construction wetland loss Temp NA NA 89 x 12 ft.
742 s.f.PC-Wetland 9-AM PEM 40.496635 -80.349641 NA NA Post-construction wetland loss Temp NA NA 44 x 23 ft.
523 s.f.PC-Stream 9-37 Intermittent 40.496514 -80.349550 UNT to Tributary 33750 to Raccoon Creek WWF Post-construction channel loss Temp 188 x 3 ft. 566 s.f. 188 x 103 ft. 19,364 s.f. NA PC-Wetland 9-AN PFO 40.496002 -80.349259 NA NA Post-construction conversion PFO to PEM Temp NA NA 37 x 27 ft.
566 s.f.PC-Wetland 9-AO PEM 40.496422 -80.349285 NA NA Post-construction wetland loss Temp NA NA 40 x 19 ft.
523 s.f.Wetland 10-Q #1 PEM 40.489168 -80.358032 NA NA Recovered, unauthorized impact by pipeline installation. Temp NA NA 286 x 122 ft.
18,382 s.f.Wetland 10-Q #2 PEM 40.488212 -80.358978 NA NA Recovered, unauthorized impact by pipeline installation. Temp NA NA 188 x 2 ft.
376 s.f.Temp NA NA 188 x 51 ft.
5,766 s.f.Wetland 10-Q #3 PEM 40.487243 -80.359184 NA NA Recovered, unauthorized impact by pipeline installation. Temp NA NA 381 x 49 ft.
15,290 s.f.Wetland 10-Q #4 PEM 40.486254 -80.358732 NA NA Recovered, unauthorized impact by pipeline installation. Temp NA NA 170 x 2 ft.
340 s.f.Temp NA NA 170 x 123 ft. 10,768 s.f. Proposed Impacts:
BEAVER COUNTY (STA 254+00 TO 1780+00) ACCESS Wetland 25 H PEM 40.735009 -80.152566 NA NA Temporary equipment access >200ft Temp NA NA 414 x 20 ft. 7,144 s.f. Wetland 25 H PEM 40.735243 -80.152234 NA NA Waterbar Removal Temp NA NA 67 x 15 ft.
945 s.f.Wetland W 20200423 1005 CWI PEM 40.731817 -80.155131 NA NA Waterbar Removal Temp NA NA 46 x 15 ft.
535 s.f.
PROJECT INFORMATION PA DEP/105 Structure/
Activity Unique IdentifierAquatic Resource Type Latitude dd nad83 Longitude dd nad83 Waters Name PA Code Chapter 93 Designation Work
Proposed(1)DEP Impact Type Temp/
PermWatercourse Impact Linear foot (along channe l) x Width (Top of Banks) Length and Width (feet) Floodway Impact Top of Bank Landward Length and Width (feet) Area
(square feet)Wetland Impact
Length and Width (feet) Area
(square feet)Wetland 10-G #1 PSS 40.730960 -80.157992 NA NA Temporary Disturbance for Perimeter Erosion Control for Abutting Restoration Temp NA NA 7 x 285 ft.
871 s.f.GP-ACCESS-
Wetland 10-G #2PEM 40.731132 -80.157488 NA NA GP-8 Temporary equipment crossing (timber mat) Temp NA NA 21 x 12 ft.
190 s.f.Stream 9-94 Perennial 40.731137 -80.157849 UNT 34822 to BRUSH CREEK WWF Grading w/in floodway for restoration Temp 0 155 x 32 ft. 3,920 s.f. NA Wetland 1-C PEM 40.728722 -80.162994 NA NA Temporary Disturbance for Perimeter Erosion Control for Abutting Restoration Temp NA NA 31 x 25 ft.
391 s.f.Wetland 9-BZ PEM 40.717122 -80.162900 NA NA Slope repair, removal of slide debris, planting for restoration Temp NA NA 91 x 25 ft. 1,796 s.f. Stream 9-42 Perennial 40.717080 -80.162820 Tributary 34825 to Brush Creek WWF Slope repair, removal of slide debris and planting for restoration Temp 90 x 5 ft. 373 s.f. 131 x 100 ft. 11,701 s.f. NA GP-ACCESS-
Stream 10-20Perennial 40.727708 -80.162733 Brush Creek WWF GP-8 Temporary Equipment Access for Slope Stabilization Temp 58 x 20 ft. 529 s.f. 158 x 20 ft. 2,164 s.f. NA GP-ACCESS-
Stream 9-43.1Ephemeral 40.719034 -80.162925 UNT to Trib 34825 to Brush Creek WWF GP-8 Temporary Equipment Access for Slope Stabilization Temp 10 x 20 ft 166 s.f. 76 x 100 ft. 7,635 s.f. NA GP-ACCESS-
Wetland 2-ALPEM 40.715472 -80.162935 NA NA GP-8 Temporary Equipment Access for Slope Stabilization Temp NA NA 55 x 20 ft.
804 s.f.GP-ACCESS-
Stream 9-72Perennial 40.714553 -80.162621 Trib 34824 to Brush Creek WWF GP-8 Temporary Equipment Access for Slope Stabilization Temp 5 x 20 ft.
61 s.f.203 x 100 ft. 20,384 s.f. NA GP-ACCESS-
Wetland W-20200327-1126-
JWR-APEM 40.714509 -80.162586 NA NA GP-8 Temporary Equipment Access for Slope Stabilization Temp NA NA 15 x 10 ft.
66 s.f.GP-ACCESS-
Stream 9-67Ephemeral 40.712522 -80.162615 UNT to Trib 34825 to Brush Creek WWF GP-8 Temporary Equipment Access for Slope Stabilization Temp 4 x 20 ft.
64 s.f.94 x 100 9,370 s.f. NA Wetland 9-CF PEM 40.705147 -80.172622 NA NA Grading w/in wetland for restoration Temp NA NA 212 x 20 ft. 2,831 s.f. Stream 9-81 Intermittent 40.704821 -80.172600 UNT to Tributary 36575 to Crows Run WWF Grading w/in floodway for restoration Temp GP-8 (previously authorized)1 67 x 19 ft. 1,310 s.f. NA Stream 9-82 Perennial 40.705591 -80.172675 UNT to Tributary 36575 to Crows Run WWF Grading w/in floodway for restoration Temp GP-8 (previously authorized)1 147 x 140 ft. 10,526 s.f. NA ACCESS-Wetland 9-CF PEM 40.704315 -80.172555 NA NA Temporary equipment access >200ft Temp NA NA 446 x 20 ft.
6,724 s.f.Stream 11-5 Ephemeral 40.691090 -80.183172 Tributary 36572 to Crows Run WWF Grading w/in stream channel and floodway for restoration Temp 13 x 2 ft.
19 s.f.45 x 15 ft. 270 s.f. NA Stream 11-8 Intermittent 40.686788 -80.196138 UNT to Crows Run WWF Grading w/in floodway for restoration Temp 0 54 x 44 ft. 1,950 s.f. NA
PROJECT INFORMATION PA DEP/105 Structure/
Activity Unique IdentifierAquatic Resource Type Latitude dd nad83 Longitude dd nad83 Waters Name PA Code Chapter 93 Designation Work
Proposed(1)DEP Impact Type Temp/
PermWatercourse Impact Linear foot (along channel) x Width (Top of Banks) Length and Width (feet) Floodway Impact Top of Bank Landward Length and Width (feet) Area
(square feet)Wetland Impact
Length and Width (feet)
Area
(square feet)Wetland W-20200407-0920 DWL-A PEM 40.686948 -80.202833 NA NA Waterbar Removal Temp NA NA 134 x 15 ft.
822 s.f.Wetland 13-C PSS 40.680143 -80.205356 NA NA Grading w/in wetland for restoration Temp NA NA 12 x 6 ft.
33 s.f.Stream 11-12 Perennial 40.680100 -80.205333 Pine Run WWF Grading w/in floodway and stream bank stabilization for restoration Temp 51 x 7 ft. 287 s.f. 140 x 53 ft. 5,860 s.f. NA GP-ACCESS-
Stream 11-12Perennial 40.680107 -80.205286 Pine Run WWF GP-8 Temporary Equipment Crossing Temp 17 x 12 ft. 87 s.f. 33 x 16 ft. 523 s.f. NA Stream 11-30 (Crows Run) Perennial 40.678985 -80.204919 Crows Run WWF Bank Stabilization Temp 73 x 18 ft. 897 s.f. 69 x 64 ft. 4,473 s.f. NA GP-ACCESS-
Wetland W-20200427-
1145-DWLPEM 40.679069 -80.204877 Wetland NA GP-8 Temporary Equipment Access for Slope Stabilization Temp NA NA 8 x 19 ft.
203 s.f.Stream 9-2-11 Intermittent 40.678460 -80.210577 UNT to Crows Run WWF Slope Repair, Bank Stabilization Temp 88 x 8 ft. 312 s.f. 84 x 100 ft. 5,822 s.f. NA Wetland 28-A PEM 40.678149 -80.210982 NA NA Waterbar Removal Temp NA NA 15 x 13 ft.
173 s.f.Stream 2-14 Intermittent 40.677701 -80.220032 UNT to Crows Run WWF Slope Repair Temp 0 112 x 49 ft. 5,515 s.f. NA Stream 2-15 Ephemeral 40.677737 -80.220654 UNT to Crows Run WWF Slope Repair Temp 0 280 x 40 ft. 11,180 s.f. NA Stream 2-19 Perennial 40.676400 -80.229431 UNT to Crows Run WWF Slope Repair and Bank Stabilization Temp 139 x 5 ft. 608 s.f. 134 x 56 ft. 7,533 s.f. NA Stream 27-1 (78A) Intermittent 40.676457 -80.229736 UNT to Crows Run WWF Slope Repair Temp 0 29 x 29 ft. 835 s.f. NA Stream 27-1 (78B) Intermittent 40.676327 -80.230030 UNT to Crows Run WWF Slope Repair Temp 0 49 x 22 ft. 1,078 s.f. NA Crows Run (Stream 2-20) #1 Perennial 40.673595 -80.237104 Crows Run WWF Slope Repair Temp 154 x 12 ft. 1,894 s.f. 154 x 12 ft. 1,827 s.f. NA Crows Run (Stream 2-20) #2 Perennial 40.673595 -80.237104 Crows Run WWF Vegetated Riprap Perm 154 x 7 ft. 1,111 s.f. 154 x 4 ft. 676 s.f. NA Stream 60-3 Intermittent 40.669601 -80.262857 UNT to Elkhorn Run WWF Slope Repair Temp 0 18 x 96 ft. 1,710 s.f. NA Stream 2-25 Intermittent 40.669282 -80.264565 UNT to Elkhorn Run WWF Slope Repair Temp 0 33 x 48 ft. 1,578 s.f. NA OUT-Stream S-20200401-
1417-DWLEphemeral 40.669292 -80.264439 UNT to Elkhorn Run WWF Outfall Perm 0 6 x 6 ft.
36 s.f.NA Stream S-20200401-
1417-DWLEphemeral 40.669294 -80.264523 UNT to Elkhorn Run WWF Slope Repair Temp 0 55 x 32 ft. 1,780 s.f. NA Stream 2-24 (Elkhorn Run) #1 Perennial 40.668917 -80.269928 Elkhorn Run WWF Slope Repair Temp 0 155 x 26 ft. 4,097 s.f. NA Stream 2-24 (Elkhorn Run) #2 Perennial 40.668737 -80.270145 Elkhorn Run WWF Grading w/in stream channel and floodway for restoration Temp 117 x 22 ft. 469 s.f. 270 x 57 ft. 10,846 s.f. NA
PROJECT INFORMATION PA DEP/105 Structure/
Activity Unique IdentifierAquatic Resource Type Latitude dd nad83 Longitude dd nad83 Waters Name PA Code Chapter 93 Designation Work
Proposed(1)DEP Impact Type Temp/
PermWatercourse Impact Linear foot (along channel) x Width (Top of Banks) Length and Width (feet) Floodway Impact Top of Bank Landward Length and Width (feet) Area
(square feet)Wetland Impact Length and Width (feet) Area (square feet) Wetland W-20200317-1127 DWL PEM 40.668975 -80.270241 NA NA Grading w/in wetland for restoration Temp NA NA 14 x 6 ft.
41 s.f.Stream 2-29 Perennial 40.651551 -80.277166 Trib 36549 to Elkhorn Run Floodway WWF Slope Repair Temp 0 87 x 44 ft. 3,836 s.f. NA GP-ACCESS-
Wetland W-20200330-
1546-DWLPEM 40.651391 -80.277103 Wetland NA GP-8 Temporary Equipment Access for Slope Stabilization Temp NA NA 17 x 12 ft.
206 s.f.GP-ACCESS-
Wetland W-20200330-
1615-DWL-BPEM 40.649212 -80.279033 Wetland NA GP-8 Temporary Equipment Access for Slope Stabilization Temp NA NA 20 x 17 ft.
343 s.f.GP-ACCESS-
Wetland 2-FPEM 40.636204 -80.296495 NA NA GP-8 Temporary equipment crossing (timber mat) Temp NA NA 61 x 37 ft.
1,045 s.f.Stream 2-9 Perennial 40.636082 -80.296679 WWF Grading w/in floodway for restoration Temp 0 93 x 31 ft. 2,614 s.f. NA Wetland 2-R #1 PEM 40.629297 -80.303134 NA NA Waterbar Removal Temp NA NA 42 x 11 ft.
342 s.f.Wetland 2-R #2 PEM 40.629207 -80.303192 NA NA Grading w/in wetland for restoration Temp NA NA 64 x 27 ft.
741 s.f.Stream 2-31 Intermittent 40.629233 -80.303218 Logtown Run WWF Grading w/in floodway for restoration Temp 0 76 x 64 ft. 2,701 s.f. NA Stream S-20200418-
1236-JWR #2Ephemeral 40.626272 -80.305451 UNT to Raccoon Creek WWF Temporary floodway impact due to BMP installation for adjacent restroration Temp 0 67 x 50 ft. 3,240 s.f. NA GP-ACCESS-
Stream 9-135Ephemeral 40.625485 -80.305623 UNT to Raccoon Creek WWF GP-8 Temporary Equipment Access for Slope Stabilization Temp 23 x 20 ft. 298 s.f. 161 x 20 ft. 2,937 s.f. NA GP-ACCESS-
Stream 9-138Intermittent 40.624625 -80.306145 UNT to Raccoon Creek WWF GP-8 Temporary Equipment Access for Slope Stabilization Temp 20 x 2 ft.
40 s.f.175 x 20 ft. 3,500 s.f. NA Stream 9-138 Intermittent 40.624694 -80.306228 UNT to Raccoon Creek WWF Grading w/in stream channel and floodway for restoration Temp 80 x 2 ft. 180 s.f. 79 x 48 ft. 2,625 s.f. NA GP-ACCESS-
Stream 9-137Intermittent 40.624816 -80.306083 UNT to Raccoon Creek WWF GP-8 Temporary Equipment Access for Slope Stabilization Temp 0 58 x 20 ft. 1,150 s.f. NA Stream 9-137 Intermittent 40.624722 -80.306008 UNT to Raccoon Creek WWF Grading w/in stream channel and floodway for restoration Temp 44 x 7 ft. 123 s.f 59 x 52 ft. 1,930 s.f. NA GP-ACCESS-
Stream 9-136Perennial 40.625450 -80.305642 UNT to Raccoon Creek WWF GP-8 Temporary Equipment Access for Slope Stabilization Temp 8 x 20 ft. 156 s.f. 163 x 20 ft. 2,746 s.f. NA Stream 9-136 (RP-108) Perennial 40.624532 -80.305920 UNT to Raccoon Creek WWF Graing w/in stream channel and floodway for restoration Temp 20 x 10 ft. 21 s.f. 103 x 53 ft. 4,801 s.f. NA Stream 9-136 (RP-108A) Perennial 40.623120 -80.306449 UNT to Raccoon Creek WWF Graing w/in stream channel and floodway for restoration Temp 13 x 3 ft.
21 s.f.50 x 50 ft. 2,587 s.f. NA OUT-Stream S-20200402-
1440-DWLEphemeral 40.621966 -80.309829 UNT to Raccoon Creek WWF Outfall Perm 24 x 4 ft.
96 s.f.25 x 43 ft. 1,072 s.f. NA Stream S-20200402-
1440-DWLEphemeral 40.621966 -80.309829 UNT to Raccoon Creek WWF Slope Repair Temp 0 25 x 43 ft. 1,072 s.f. NA
PROJECT INFORMATION PA DEP/105 Structure/
Activity Unique IdentifierAquatic Resource Type Latitude dd nad83 Longitude dd nad83 Waters Name PA Code Chapter 93 Designation Work
Proposed (1)DEP Impact Type Temp/
PermWatercourse Impact Linear foot (along channel) x Width (Top of Banks) Length and Width (feet) Floodway Impact Top of Bank Landward Length and Width (feet) Area
(square feet)Wetland Impact
Length and Width (feet) Area
(square feet)OUT-Stream 13-109 Ephemeral 40.620813 -80.312694 UNT to Raccoon Creek WWF Outfall Perm 25 x 6 ft. 150 s.f. 25 x 106 ft. 2,650 s.f. NA OUT-Stream 9-10-24 Perennial 40.621210 -80.313836 Trib 33581 to Raccoon Creek WWF Outfall Perm 0 9 x 13 ft. 117 s.f. NA Stream 9-10-24 Perennial 40.621210 -80.313836 Trib 33581 to Raccoon Creek WWF Slope Repair Temp 0 219 x 49 ft. 10,730 s.f. NA Stream 9-29 Intermittent 40.616603 -80.329037 UNT to Raccoon Creek WWF Slope Repair Temp 0 113 x 34 ft. 3,859 s.f. NA OUT-Stream 9-28 (Raccoon Creek) Perennial 40.616658 -80.329217 Raccoon Creek WWF Outfall Perm 0 68 x 6 ft. 402 s.f.. NA Stream 9-28 (Raccoon Creek) Perennial 40.616733 -80.329192 Raccoon Creek WWF Slope Repair Temp 0 63 x 123 ft. 7,642 s.f. NA Wetland 9-AG (2-AG) PEM 40.611579 -80.330028 NA NA Grading w/in wetland for restoration Temp NA NA 115 x 37 ft.
3,013 s.f.GP-ACCESS-
Wetland 20200421-
1215-CWIPEM 40.610475 -80.330144 NA NA GP-8 Temporary Equipment Access Temp NA NA 144 x 41 ft.
3,920 s.f.OUT-Stream 37-1 Ephemeral 40.607685 -80.325821 UNT to Trib 33580 to Raccoon Creek WWF Outfall Perm 0 60 x 25 ft 1,500 s.f. NA Stream 9-113 Perennial 40.606406 -80.327059 Trib 33580 to Raccoon Creek Floodway WWF Slope Repair Temp 0 54 x 38 ft 2,070 s.f. NA OUT-Stream 9-113 Perennial 40.606457 -80.327048 Trib 33580 to Raccoon Creek Floodway WWF Outfall Perm 0 4 x 4 ft
16 s.f.NA Stream 9-112 Ephemeral 40.606797 -80.327088 UNT to Trib 33580 to Raccoon Creek WWF Slope Repair Temp 0 134 x 53 ft 7,066 s.f. NA OUT-Stream 9-112 #1 Ephemeral 40.606533 -80.327039 UNT to Trib 33580 to Raccoon Creek WWF Outfall Perm 0 4 x 4 ft
16 s.f..NA OUT-Stream 9-112 #2 Ephemeral 40.606589 -80.327032 UNT to Trib 33580 to Raccoon Creek WWF Outfall Perm 0 4 x 4 ft
16 s.f..NA Stream 9-112.1 Intermittent 40.606808 -80.326991 UNT to Trib 33580 to Raccoon Creek WWF Slope Repair Temp 0 59 x 24 ft. 1,431 s.f. NA OUT-Stream 9-112.1 Intermittent 40.606858 -80.327001 UNT to Trib 33580 to Raccoon Creek WWF Outfall Perm 0 4 x 4 ft
16 s.f.NA Stream 9-114 Perennial 40.606293 -80.327474 UNT to Trib 33580 to Raccoon Creek Floodway WWF Slope Repair Temp 0 95 x 41 ft. 3,892 s.f. NA Wetland W-20200403-1342 DWL PEM 40.607442 -80.327084 NA NA Slope Repair Perm NA NA 24 x 23 ft.
549 s.f.Wetland W-20200403-1114 DWL PEM 40.606675 -80.327267 NA NA Slope Repair Perm NA NA 16 x 11 ft.
175 s.f.Stream 9-63 Perennial 40.593311 -80.328129 Frames Run WWF Slope Repair, Grading w/in stream channel and floodway for restoration Temp 373 x 15 ft. 5,591 s.f. 315 x 100 ft. 31,505 s.f. NA
PROJECT INFORMATION PA DEP/105 Structure/
Activity Unique IdentifierAquatic Resource Type Latitude dd nad83 Longitude dd nad83 Waters Name PA Code Chapter 93 Designation Work
Proposed(1)DEP Impact Type Temp/
PermWatercourse Impact Linear foot (along channel) x Width (Top of Banks) Length and Width (fe et) Floodway Impact Top of Bank Landward Length and Width (feet) Area
(square feet)Wetland Impact Length and Width (feet) Area (square feet) Wetland 73-D PEM 40.592974 -80.327675 NA NA Temporary impact due to pump-around and coffer dam installation for adjacent stream restoration Temp NA NA 21 x 5 ft.
49 s.f.Stream 9-164 Ephemeral 40.585055 -80.333557 UNT to Tributary 33594 to Service Creek WWF Grading w/in stream channel and floodway for restoration Temp 111 x 15 ft. 848 s.f. 174 x 93 ft. 10,644 s.f. NA Wetland W-20200421-1025 JWR PEM 40.584982 -80.333651 NA NA Grading w/in wetland for restoration Temp NA NA 12 x 9 ft.
91 s.f.Stream 9-162 Perennial 40.584505 -80.335892 Trib 33594 to Service Creek WWF Slope Repair Temp 0 145 x 52 ft. 7,561 s.f. NA Stream 9-2-34 Perennial 40.576691 -80.334797 UNT to Service Creek WWF Slope Repair Temp 0 108 x 14 ft. 1,532 s.f. NA OUT-Stream 9-2-34 Perennial 40.576522 -80.334857 UNT to Service Creek WWF Outfall Perm 0 4 x 3 ft.
12 s.f.NA GP-ACCESS-
Wetland W-20200415-
1132-JWR-CPEM 40.575010 -80.331003 Wetland NA GP-8 Temporary Equipment Access for Slope Stabilization Temp NA NA 67 x 26 ft. 963 s.f. Stream 9-151 Ephemeral 40.573296 -80.331826 UNT to Service Creek WWF Grading w/in stream channel and floodway for restoration Temp 140 x 11 ft. 1343 s.f. 97 x 71 ft. 4,791 s.f. NA Stream 9-152 Perennial 40.573512 -80.332052 UNT to Service Creek WWF Grading w/in stream channel and floodway for restoration Temp 135 x 12 ft. 733 s.f. 120 x 110 ft. 10,060 s.f. NA Wetland 31-A PEM 40.562223 -80.330260 NA NA Waterbar Removal Temp NA NA 84 x 15 ft. 737 s.f. Wetland 9-EI PEM 40.561632 -80.329976 NA NA Grading w/in wetland for restoration Temp NA NA 59 x 40 ft. 1469 s.f. Stream 9-153 Perennial 40.561537 -80.329957 UNT to Tributary 33659 of Raccoon Creek WWF Grading w/in floodway for restoration Temp GP-8 (previously authorized)1 145 x 70 ft. 5,689 s.f. NA Wetland 9-EN PEM 40.558901 -80.334310 NA NA Waterbar Removal Temp NA NA 111 x 39 ft. 790 s.f. ACCESS-
Stream 2-36Perennial 40.551972 -80.34066 Tributary 33660 to Raccoon Creek WWF Temporary equipment crossing; fill over culvert exceeds GP threshold Temp 20 x 17 ft. 348 s.f 227 x 125 ft. 17,032 s.f. NA Stream 2-35 Perennial 40.545196 -80.343404 UNT to Obney Run WWF Slope Repair, Bank Stabilization Temp 110 x 11 ft. 1,232 s.f. 99 x 50 ft. 4,969 s.f. NA Stream 9-109 (Stream 13- 107B) Perennial 40.534851 -80.351353 UNT to Raccoon Creek WWF Slope Repair, Bank Stabilization Temp 152 x 16 ft. 864 s.f. 154 x 126 ft. 9,810 s.f. NA Wetland 42-D (RP-151) PEM 40.534747 -80.351206 NA NA Temporary Disturbance for Abutting Channel Restoration Temp NA NA 146 x 31 ft. 1,801 s.f. Wetland 27-I PEM 40.528063 -80.351112 NA NA Waterbar Removal Temp NA NA 28 x 9 ft. 174 s.f. Stream 10-52 (Raccoon Creek) Perennial 40.514074 -80.351202 Raccoon Creek WWF Grading w/in floodway for restoration Temp 0 20 x 17 ft. 348 s.f. NA
PROJECT INFORMATION PA DEP/105 Structure/
Activity Unique IdentifierAquatic Resource Type Latitude dd nad83 Longitude dd n ad83 Waters Name PA Code Chapter 93 Designation Work
Proposed(1)DEP Impact Type Temp/
PermWatercourse Impact Linear foot (along channel) x Width (Top of Banks) Length and Width (feet) Floodway Impact Top of Bank Landward Length and Width (feet) Area
(square feet)Wetland Impact Length and Width (feet) Area (square feet) Wetland W-20200401-1043 JWR-A PEM 40.513270 -80.351006 NA NA Removal of fill. Temp NA NA 17 x 53 ft. 906 s.f. Stream 9-36 Perennial 40.509608 -80.350739 UNT to Raccoon Creek WWF Grading w/in stream channel and floodway for restoration Temp 280 x 5 ft. 1,282 s.f. 280 x 42 ft. 7,377 s.f. NA Wetland 9-AK PEM 40.508450 -80.350940 NA NA Temporary Disturbance for Perimeter Erosion Control for Abutting Restoration Temp NA NA 8 x 64 ft. 338 s.f. Stream S-20200401-
0911-JWRIntermittent 40.508450 -80.350940 UNT to Raccoon Creek WWF Grading w/in stream channel and floodway for restoration Temp 77 x 3 ft. 187 s.f. 105 x 94 ft. 5,232 s.f. NA GP-ACCESS-
Stream S-20200401-
0911-JWRIntermittent 40.508449 -80.350915 UNT to Raccoon Creek WWF GP-8 Temporary Equipment Access for Slope Stabilization Temp 0 34 x 20 ft. 757 s.f. NA GP-ACCESS-
Wetland W-20200331-
1310-JWR-APEM 40.508000 -80.351000 NA NA GP-8 Temporary Equipment Access for Slope Stabilization Temp NA NA 20 x 18 ft. 365 s.f. GP-ACCESS-
Wetland W-20200331-
1310-JWR-BPEM 40.508000 -80.351000 NA NA GP-8 Temporary Equipment Access for Slope Stabilization Temp NA NA 20 x 30 ft. 599 s.f. Stream 9-37 Intermittent 40.496315 -80.349556 UNT to Tributary 33750 to Raccoon Creek WWF Grading w/in stream channel and floodway for restoration Temp 331 x 3 ft. 784 s.f. 305 x 108 ft. 29,011 s.f. NA Stream 10-43 Intermittent 40.495966 -80.349247 UNT to Raccoon Creek WWF Grading w/in floodway for restoration Temp 0 76 x 20 ft. 566 s.f. NA Wetland W-20200409-1558 DWL PEM 40.496491 -80.349309 NA NA Grading w/in wetland for restoration Temp NA NA 89 x 6 ft. 367 s.f. ACCESS-
Wetland 10-QPEM 40.489555 -80.357903 NA NA Temporary equipment crossing >200ft. Temp NA NA 914 x 20 ft. 16,840 s.f. GP-ACCESS-
Wetland 15-APEM 40.490033 -80.357365 NA NA GP-8 Temporary Equipment Access for Slope Stabilization Temp NA NA 60 x 20 ft. 1,199 s.f. Wetland 15-A PEM 40.490521 -80.356911 NA NA Temporary E&S Controls Temp NA NA 37 x 25 ft. 573 s.f. OUT-Stream 10-44 Perennial 40.490136 -80.357283 UNT to Raccoon Creek WWF Outfall Perm 0 5 x 5
25 s.f.NA Stream 10-44 Perennial 40.489900 -80.357212 UNT to Raccoon Creek WWF Temporary Staging Areas Temp 0 104 x 123 ft. 12,796 s.f. NA Stream 10-42 Perennial 40.495531 -80.349389 Trib 33750 to Raccoon Creek WWF Slope Repair Temp 0 125 x 50 6,250 s.f. NA E1007220-026; ETC Northeast Pipeline, LLC, 6051 Wallace Road Extension, Third Floor, Wexford, PA 15090, Findlay Township, Allegheny County, Center, Conway, Independence, New Sewickley, Racoon Township(s), Beaver County, Jackson Township, Butler County, Robinson, Smith Townships, Washington County, ACOE Pittsburgh District.
The Revolution Pipeline project was originally permitted to install a 40.5-mile-long, 24-inch diameter steel natural gas pipeline that connects wells in Butler and Beaver counties to a natural gas processing facility in Washington County, Pennsylvania. This application is for the proposed restoration and on-site mitigation of aquatic resources impacted by the initial Revolution Pipeline construction, slope failures along the Revolution Pipeline ROW and the reconstruction of slope failures along the Revolution Pipeline ROW, the use of off-site mitigation for permanent impacts that cannot be restored on-site, unavoidable impacts to waters associated with landslide remediation and slope stabilization, and temporary impacts to waters for access for restoration and remediation activities.
The project is located within the Aliquippa, Baden, Beaver, Clinton, Evans City and Zelienople USGS 7 1/2 Minute Quadrangle Map.
See E0207220-038; E0407220-023 and E6307220-027 for additional impacts associated with this project.
Historic Impacts from the construction of the Revolution Pipeline include:
BUTLER COUNTY (STA 0+00 TO 254+00) Structure/
Activity Unique IdentifierAquatic Resource Type Latitude dd nad83 Longitude dd nad83 Waters Name PA Code Chapter 93 Designation Work
Proposed(1)DEP Impact Type Temp/
PermWatercourse Impact Linear foot (along channel) x Width (Top of Banks) Length and Width (feet) Floodway Impact Top of Bank Landward Length and Width (feet) Area
(square feet)Wetland Impact Length and Width (feet) Area
(square feet)PC-Stream 25-1 Intermittent 40.783374 -80.081030 UNT to Tributary 35017 to Breakneck Creek WWF Post-construction realignment of stream channel to existing pond Temp 62 x 6 ft. 348 s.f. 0 NA PC-Wetland 9-J #1 PSS 40.783764 -80.081317 NA NA Post-construction wetland loss Temp NA NA 80 x 75 ft.
6,839 s.f.PC-Wetland 9-J #2 40.783683 -80.080882 Perm NA NA 103 x 93 ft. 3,267 s.f. PC-Stream 9-97 Intermittent 40.783320 -80.081675 UNT to Tributary 35017 to Breakneck Creek WWF Post-construction channel loss Perm 287 x 2 ft. 566 s.f 287 x 102 ft. 29,272 s.f. NA PC-Wetland 9-T PEM 40.777441 -80.117721 NA NA Post-construction wetland loss Temp NA NA 54 x 28 ft.
784 s.f.PC-Wetland 9-U PEM 40.777588 -80.121228 NA NA Post-construction conversion PSS to PEM Temp NA NA 64 x 25 ft.
1,002 s.f.PC-Wetland 2-J PEM 40.774674 -80.124875 NA NA Post-construction conversion PFO to PEM Temp NA NA 96 x 44 ft.
2,570 s.f.Wetland 9-DQ PEM 40.769696 -80.140968 NA NA Recovered, unauthorized impact by temporary access for pipeline installation. Temp NA NA 7 x 6 ft.
38 s.f.Wetland 9-DO PEM 40.770082 -80.141709 NA NA Recovered, unauthorized impact by temporary access for pipeline installation. Temp NA NA 15 x 4 ft.
39 s.f.PC-Stream 9-91 Ephemeral 40.769826 -80.146502 UNT to a UNT to Tributary 34909 to Glade Run WWF Post-construction channel loss Temp 55 x 3 ft. 174 s.f. 55 x 102 ft. 5,610 s.f. NA PC-Stream 9-92 Ephemeral 40.769910 -80.146557 UNT to a UNT to Tributary 34909 to Glade Run WWF Post-construction channel loss Temp 58 x 4 ft. 218 s.f 58 x 104 ft. 6,032 s.f. NA Proposed Impacts:
BUTLER COUNTY (STA 0+00 TO 254+00) Project Information PA DEP/105 Structure/
Activity Unique IdentifierAquatic Resource Type Latitude dd nad83 Longitude dd nad83 Waters Name PA Code Chapter 93 Designation Work
Proposed(1)DEP Impact Type Temp/
PermWatercourse Impact Linear foot (along channel) x Width (Top of Banks) Length and Width (feet) Floodway Impact Top of Bank Landward Length and Width (feet) Area
(square feet)Wetland Impact Length and Width (feet) Area
(square feet)Stream 25 1 Intermittent 40.783448 -80.081179 UNT to Tributary 35017 to Breakneck Creek WWF Grading w/in floodway for restoration Temp GP 8 (previously authorized)1 203 x 106 ft. 13,024 s.f. NA Wetland W 20200424 0940 MRM PSS 40.782530 -80.081215 NA NA Grading w/in wetland for stream restoration Temp NA NA 66 x 54 ft.
2,831 s.f.Wetland 9 K PEM 40.776968 -80.103685 NA NA Waterbar Removal Temp NA NA 19 x 15 ft.
268 s.f.Stream 9 11 Ephemeral 40.776960 -80.106013 UNT to Trib 34910 To Glade Run WWF Temporary access and stockpiling for riparian plantings Temp 0 91 x 31 ft. 1,430 s.f. NA GP ACCESS Wetland W 20200416 1045 DWL B PEM 40.776862 -80.106156 NA NA GP 8 Temporary equipment crossing (timber mat) Temp NA NA 16 x 10 ft.
109 s.f.GP ACCESS Wetland W 20200416 1045 DWL C PEM 40.776863 -80.106011 NA NA GP 8 Temporary equipment crossing (timber mat) Temp NA NA 18 x 12 ft.
145 s.f.Wetland W 20200423 1220 CWI A PEM 40.777374 -80.117507 NA NA Waterbar Removal Temp NA NA 27 x 15 ft.
360 s.f.Wetland 9 T PEM 40.777396 -80.117701 NA NA Grading w/in wetland for restoration Temp NA NA 22 x 15 ft.
164 s.f.Stream 9 18 Perennial 40.777449 -80.117648 UNT to Tributary 34910 to Glade Run WWF Grading w/in floodway for restoration Temp GP 8 (previously authorized)1 108 x 74 ft. 5,272 s.f. NA Wetland 2 J PEM 40.774729 -80.124884 NA NA Waterbar Removal Temp NA NA 40 x 15 ft.
417 s.f.Wetland 25 F PEM 40.771324 -80.137431 NA NA Waterbar Removal Temp NA NA 75 x 15 ft.
743 s.f.Wetland W 20200318 1324 DWL A PEM 40.769824 -80.144880 NA NA Waterbar Removal Temp NA NA 37 x 15 ft.
397 s.f.Stream 10 14 Intermittent 40.769858 -80.146470 UNT to Tributary 34909 to Glade Run WWF Grading w/in floodway for restoration Temp GP 8 (previously authorized)1 76 x 64 ft. 4,381 s.f. NA Wetland 9 CO PEM 40.769876 -80.146543 NA NA Grading w/in wetland for adjacent stream restoration Temp NA NA 46 x 77 ft.
2,039 s.f.Wetland 9 CP PEM 40.769819 -80.146462 NA NA Grading w/in wetland for adjacent stream restoration Temp NA NA 17 x 76 ft.
907Wetland 65 H PEM 40.765731 -80.152841 NA NA Waterbar Removal Temp NA NA 118 x 15 ft.
1,210 s.f.E6307220-027; ETC Northeast Pipeline, LLC, 6051 Wallace Road Extension, Third Floor, Wexford, PA 15090, Findlay Township, Allegheny County, Center, Conway, Independence, New Sewickley, Racoon Township(s), Beaver County, Jackson Township, Butler County, Robinson, Smith Townships, Washington County, ACOE Pittsburgh District.
The Revolution Pipeline project was originally permitted to install a 40.5-mile-long, 24-inch diameter steel natural gas pipeline that connects wells in Butler and Beaver counties to a natural gas processing facility in Washington County, Pennsylvania. This application is for the proposed restoration and on-site mitigation of aquatic resources impacted by the initial Revolution Pipeline construction, slope failures along the Revolution Pipeline ROW and the reconstruction of slope failures along the Revolution Pipeline ROW, the use of off-site mitigation for permanent impacts that cannot be restored on-site, unavoidable impacts to waters associated with landslide remediation and slope stabilization, and temporary impacts to waters for access for restoration and remediation activities.
The project is located within the Aliquippa, Baden, Beaver, Clinton, Evans City and Zelienople USGS 7 1/2 Minute Quadrangle Map.
See E0407220-023; E1007220-026 and E0207220-038 for additional impacts associated with this project.
Historic Impacts from the construction of the Revolution Pipeline include:
WASHINGTON COUNTY (STA 1914+00 TO 2152+58) PC-Wetland 11-H PSS 40.454739 -80.336924 NA NA Post-construction conversion PSS to PEM Temp NA NA 140 x 75 ft. 9,540 s.f. Wetland 11-L PEM 40.448069 -80.334953 NA NA Recovered, unauthorized impact by temporary access for pipeline installation. Temp NA NA 2 x 1 ft.
2 s.f.PC-Wetland 9-FK PFO 40.443979 -80.336085 NA NA Post-construction conversion PFO to PEM Temp NA NA 59 x 50 ft.
2,875 s.f.PC-Wetland 9-EZ PFO 40.439952 -80.340274 NA NA Post-construction conversion PFO to PEM Temp NA NA 71 x 60 ft.
3,093 s.f.Wetland W-20200408-
0958-DWLPEM 40.438369 -80.345962 NA NA Recovered, unauthorized impact by pipeline installation. Temp NA NA 142 x 2 ft.
284 s.f.Temp NA NA 142 x 58 ft. 3,506 s.f Wetland 9-EW PEM 40.437806 -80.346522 NA NA Recovered, unauthorized impact by temporary access for pipeline installation. Temp NA NA 24 x 17 ft.
348 s.f.Stream 10-302 Ephemeral 40.423734 -80.352405 UNT to Trib 33805 to Little Raccoon Run WWF Recovered, unauthorized impact by pipeline installation. Temp 84 x 1 ft.
87 s.f.84 x 101 ft. 8,494 s.f. NA PC-Wetland WPA-CDK-003 PFO 40.415498 -80.345441 NA NA Post-construction conversion PFO to PEM Temp NA NA 43 x 39 ft. 1,176 s.f. Proposed Impacts:
WASHINGTON COUNTY (STA 1914+00 TO 2152+58) GP-ACCESS-
Wetland 9-EVPEM 40.438000 -80.346500 NA NA GP-8 Temporary Equipment Access for Slope Stabilization Temp NA NA 70 x 20
1,424 s.f.GP-ACCESS-
Wetland 9-FHPEM 40.435290 -80.354900 NA NA GP-8 Temporary Equipment Access for Slope Stabilization Temp NA NA 20 x 20 ft.
422 s.f.Wetland 30-BA PEM 40.428765 -80.352872 NA NA Waterbar Removal Temp NA NA 131 x 15 ft. 1,818 s.f.
[Continued on next Web Page]
No part of the information on this site may be reproduced for profit or sold for profit.This material has been drawn directly from the official Pennsylvania Bulletin full text database. Due to the limitations of HTML or differences in display capabilities of different browsers, this version may differ slightly from the official printed version.