§ 103.32. Cost breakdown.
A breakdown of, and supporting documentation for, the total construction cost of the treatment works is required, including intercepting sewers and pumping stations which are integral parts of the treatment facilities, the cost of land and rights of way acquired after September 1, 1937, total engineering costs covering the preparation of plans and specifications, supervision and inspection of construction, legal and financial expenses, and interest during construction with a basis for proration of the costs ascribed to eligible facilities. Supporting documentation shall include, but not be limited to:
(1) One copy of itemized invoices.
(2) One copy of proof of payment in the form of cancelled checks or signed payment requisitions.
Authority The provisions of this § 103.32 amended under the act of August 20, 1953 (P. L. 1217, No. 339) (35 P. S. § § 701703); The Clean Streams Law (35 P. S. § § 691.1691.1001); and section 1920-A of The Administrative Code of 1929 (71 P. S. § 510-20).
Source The provisions of this § 103.32 adopted September 2, 1971, effective September 3, 1971, 1 Pa.B. 1804; amended January 22, 1982, effective January 23, 1982, 12 Pa.B. 382; corrected December 30, 1982, effective January 23, 1982, 13 Pa.B. 17; amended September 27, 1991, effective September 28, 1991, 21 Pa.B. 4397. Immediately preceding text appears at serial page (78979).
No part of the information on this site may be reproduced for profit or sold for profit.
This material has been drawn directly from the official Pennsylvania Code full text database. Due to the limitations of HTML or differences in display capabilities of different browsers, this version may differ slightly from the official printed version.