§ 105.107. Final inspection.
Within 10 days after the completion of work on a dam authorized by the Department, the permittee or owner shall schedule a final project inspection with the Department. The final inspection must include the permittee or owner, the permittee or owners supervising engineer, and the Departments field representative. Upon conclusion of this final inspection, the Departments field representative will present the permittee or owner with a list of any deficient items, if necessary. A follow-up final inspection may be required by the Department. At the discretion of the Department, the final inspection may be waived for projects authorized by Letter of Amendment or Letter of Authorization.
Authority The provisions of this § 105.107 amended under section 5 of the Dam Safety and Encroachments Act (32 P. S. § 693.5).
Source The provisions of this § 105.107 adopted September 26, 1980, effective September 27, 1980, 10 Pa.B. 3843; amended January 7, 2011, effective January 8, 2011, 41 Pa.B. 219. Immediately preceding text appears at serial page (207725).
Cross References This section cited in 25 Pa. Code § 105.88 (relating to dam permit issuance); and 25 Pa. Code § 105.445 (relating to waiver of certain requirements).
No part of the information on this site may be reproduced for profit or sold for profit.
This material has been drawn directly from the official Pennsylvania Code full text database. Due to the limitations of HTML or differences in display capabilities of different browsers, this version may differ slightly from the official printed version.