§ 127.13. Extensions.
(a) Approval granted by the Department will be valid for a limited time, as specified by the Department in the approval. Except as provided in § § 127.11a and 127.215 (relating to reactivation of sources; and reactivation), at the end of the time, if the construction, modification, reactivation or installation has not been completed, a new plan approval application or an extension of the previous approval will be required.
(b) If the construction, modification or installation is not commenced within 18 months of the issuance of the plan approval or if there is more than an 18-month lapse in construction, modification, or installation, a new plan approval application that meets the requirements of this subchapter and Subchapters D and E (relating to prevention of significant deterioration of air quality; and new source review) shall be submitted. The Department may extend the 18-month period upon a satisfactory showing that an extension is justified.
Source The provisions of this § 127.13 adopted September 10, 1971, effective September 11, 1971, 1 Pa.B. 1804; amended March 3, 1972, effective March 20, 1972, 2 Pa.B. 383; amended March 17, 1989, effective March 18, 1989, 19 Pa.B. 1169; amended November 25, 1994, effective November 26, 1994, 24 Pa.B. 5899; amended May 18, 2007, effective May 19, 2007, 37 Pa.B. 2365. Immediately preceding text appears at serial page (313710).
No part of the information on this site may be reproduced for profit or sold for profit.
This material has been drawn directly from the official Pennsylvania Code full text database. Due to the limitations of HTML or differences in display capabilities of different browsers, this version may differ slightly from the official printed version.