§ 211.161. Detonating cords.
(a) Detonating cord shall be cut from the supply roll immediately after placement in the blast hole. A sufficient length of downlines shall be left at the top of the blast hole for connections to trunk lines. The supply roll shall be immediately removed from the site. Scrap pieces of detonating cord shall be destroyed after connections are made.
(b) A trunk line shall be covered with at least 12 inches (0.30 meter) of earth or sand, unless otherwise authorized by the Department.
(c) Detonating cord may not be spliced if the resulting splice will fall within a blast hole.
No part of the information on this site may be reproduced for profit or sold for profit.
This material has been drawn directly from the official Pennsylvania Code full text database. Due to the limitations of HTML or differences in display capabilities of different browsers, this version may differ slightly from the official printed version.