Subchapter B. GENERAL FACILITY STANDARDS
Sec.
264a.11. Identification number and transporter license.
264a.12. Required notices.
264a.13. General and generic waste analysis.
264a.15. General inspection and construction inspection requirements.
264a.18. Location standards.
Cross References This section cited in 25 Pa. Code § 270a.60 (relating to permits by rule).
§ 264a.11. Identification number and transporter license.
In addition to the requirements incorporated by reference, a person or municipality who owns or operates a hazardous waste management facility may not accept hazardous waste for treatment, storage or disposal from a transporter who has not received an EPA identification number and a license from the Department, except as otherwise provided. The licensing requirement does not apply to very small quantity generators transporting their own hazardous waste provided that the very small quantity generator is in compliance with § 262a.14(b) (relating to conditions for exemption for a very small quantity generator), transporters transporting recyclable materials utilized for precious metal recovery in compliance with § 266a.70(1) (relating to applicability and requirements) or universal waste transporters in compliance with § 266b.50 (relating to applicability).
Authority The provisions for this § 264a.11 amended under sections 105, 402 and 501 of the Solid Waste Management Act (35 P.S. § § 6018.105, 6018.402 and 6018.501); sections 303 and 305(e)(2) of the Hazardous Sites Cleanup Act (35 P.S. § § 6020.303 and 6020.305(e)(2)); and section 1920-A of the Administrative Code of 1929 (71 P.S. § 510-20).
Source The provisions of this § 264a.11 amended July 17, 2020, effective July 18, 2020, 50 Pa.B. 3581.
Cross References This section cited in 25 Pa. Code § 270a.60 (relating to permits-by-rule); and 25 Pa. Code § 298.51 (relating to notification).
§ 264a.12. Required notices.
The substitution of terms as specified in § 260a.3(a)(1) (relating to terminology and citations related to Federal regulations) does not apply to 40 CFR 264.12 (relating to required notices).
§ 264a.13. General and generic waste analysis.
(a) In addition to the requirements incorporated by reference, before an owner or operator of a facility that treats, stores or disposes of a specific hazardous waste from a specific generator for the first time, the owner or operator shall submit to the Department a notification that the facility intends to accept an additional waste stream generated by the specified generator. This notification shall include information that is specified in the facilitys permit.
(b) If the notification information required in subsection (a) is not required by the facilitys permit, the owner or operator shall submit the information required by § 265a.13 (relating to general and generic waste analysis) until the permit is amended to require the notification information.
§ 264a.15. General inspection and construction inspection requirements.
In addition to the requirements incorporated by reference, an owner or operator shall submit a schedule for construction of a hazardous waste management facility to the Department for approval. At a minimum, the schedule shall provide for inspection and approval by the Department of each phase of construction.
§ 264a.18. Location standards.
In addition to the requirements incorporated by reference, Chapter 269a (relating to siting) applies to hazardous waste treatment and disposal facilities.
Cross References This section cited in 25 Pa. Code § 270a.60 (relating to permits-by-rule).