25 Pa. Code § 273.101. Two phase process.

GENERAL


§ 273.101. Two phase process.

 A person or municipality may submit an application for a permit to operate a municipal waste landfill in two phases, known as Phase I and Phase II, in accordance with this subchapter. Approval by the Department of a Phase I application does not constitute or guarantee approval for the Phase II permit application, issuance of the permit or authority to operate a municipal waste landfill.



No part of the information on this site may be reproduced for profit or sold for profit.