PROJECT CHANGES
§ 76.41. Department approval requirements.
(a) After a project has been given tentative approval, or placed on a priority list, whichever is applicable, written approval of the Department is required for project changes which alter the approved scope of the project, substantially alter the design of the project or increase the amount of Commonwealth funds needed to complete the project.
(b) Approval of project changes under this section may not commit or obligate the Commonwealth to an increase in the amount of the grant or loan, or both, or disbursements thereunder unless the increase is agreed to by the Department.
Source The provisions of this § 76.41 adopted December 13, 1974, effective December 30, 1974, 4 Pa.B. 2529; amended January 30, 1976, effective February 16, 1976, 6 Pa.B. 157. Immediately preceding text appears at serial page (18964).
No part of the information on this site may be reproduced for profit or sold for profit.
This material has been drawn directly from the official Pennsylvania Code full text database. Due to the limitations of HTML or differences in display capabilities of different browsers, this version may differ slightly from the official printed version.