Pennsylvania Code & Bulletin
COMMONWEALTH OF PENNSYLVANIA

• No statutes or acts will be found at this website.

The Pennsylvania Code website reflects the Pennsylvania Code changes effective through 54 Pa.B. 5598 (August 31, 2024).

25 Pa. Code § 76.94. Withholding of payment.

§ 76.94. Withholding of payment.

 If the development agency, prior to receipt of the total disbursement for loan or grant, or both, fails to comply with the act or other laws of this Commonwealth applicable to the development project or demonstration project, the Department may upon reasonable notice to the development agency and the contractor withhold, in whole or part, further disbursements to the development agency pending compliance, provided, however, that payment to the contractor shall be authorized for the work which has been approved by the development agency and performed by the contractor prior to the date of the notice.

Source

   The provisions of this §  76.94 adopted January 30, 1976, effective February 16, 1976, 6 Pa.B. 157.



No part of the information on this site may be reproduced for profit or sold for profit.


This material has been drawn directly from the official Pennsylvania Code full text database. Due to the limitations of HTML or differences in display capabilities of different browsers, this version may differ slightly from the official printed version.