§ 77.595. Concurrent reclamation.
(a) Reclamation procedures, including backfilling, grading, topsoil replacement and revegetation of land that is disturbed by noncoal surface mining shall be kept concurrent with the progress of the proposed operation to the greatest extent possible in conformance with § § 77.456, 77.59277.594, this section, § 77.596 and the approved reclamation plan.
(b) If site conditions dictate that reclamation cannot begin until mineral extraction is terminated, the reasons for this delay shall be detailed in the reclamation plan required under § 77.456 (relating to reclamation information).
(c) Reclamation shall begin within 30 days of when mineral extraction is terminated, and be completed within the period specified in the approved reclamation plan.
(d) Mineral extraction is considered to be terminated when the permitted extent of the mineral reserves has been extracted.
Source The provisions of this § 77.595 adopted March 16, 1990, effective March 17, 1990, 20 Pa.B. 1643; amended January 30, 1998, effective January 31, 1998, 28 Pa.B. 619. Immediately preceding text appears at serial page (198763).
Cross References This section cited in 25 Pa. Code § 77.456 (relating to reclamation information).
No part of the information on this site may be reproduced for profit or sold for profit.
This material has been drawn directly from the official Pennsylvania Code full text database. Due to the limitations of HTML or differences in display capabilities of different browsers, this version may differ slightly from the official printed version.