§ 91.14. Time for constructing treatment works.
(a) If, in lieu of abatement, a notified party elects to provide waste treatment works and submits plans therefore, the Department, upon approving the plans will set a time within which the treatment works shall be constructed and placed in operation or will notify the party to be prepared to construct the plant upon notice from the Department, depending upon the status of the Departments program of construction for the basin in which the receiving stream lies as specified in § 91.15 (relating to basin-wide compliance).
(b) In some cases, time may be required within which to prepare plans and construct treatment works by a party responsible for stream pollution before abatement can be consummated. The Department, upon application by the party and when in its judgment the public interest warrants, may grant a limited extension of time during which the discharge of waste shall be permitted, if the party responsible therefor continues work on corrective measures.
Authority The provisions of this § 91.14 amended under section 5 of The Clean Streams Law (35 P. S. § 691.5); and section 1920-A of The Administrative Code of 1929 (71 P. S. § 510-20).
Source The provisions of this § 91.14 adopted September 2, 1971, effective September 3, 1971, 1 Pa.B. 1804; amended January 28, 2000, effective January 29, 2000, 30 Pa.B. 521. Immediately preceding text appears at serial pages (225896) to (225897).
No part of the information on this site may be reproduced for profit or sold for profit.
This material has been drawn directly from the official Pennsylvania Code full text database. Due to the limitations of HTML or differences in display capabilities of different browsers, this version may differ slightly from the official printed version.