GENERAL
§ 277.101. Two-phase process.
A person or municipality may submit an application for a permit to operate a construction/demolition waste landfill in two phases, known as Phase I and Phase II, under this subchapter. Approval by the Department of a Phase I application does not constitute or guarantee approval for the Phase II permit application, issuance of the permit or authority to operate a construction/demolition waste landfill.