25 Pa. Code § 88.305. Hydrologic balance: groundwater monitoring.

§ 88.305. Hydrologic balance: groundwater monitoring.

 (a)  Groundwater levels, subsurface flow and the quality of groundwater shall be monitored in a manner approved by the Department to determine the effects of coal refuse disposal activities on the reclaimed lands and on the quantity and quality of groundwater in the permit and adjacent areas.

 (b)  When coal refuse disposal activities may affect the groundwater systems which serve as aquifers which ensure the hydrologic balance of water use on or off the permit area, groundwater levels and groundwater quality shall be monitored. Monitoring shall include measurements from a sufficient number of sources and chemical analyses of water from aquifers that are adequate to reflect changes in groundwater quality and quantity resulting from those activities. Monitoring shall be adequate to plan for modification of coal refuse disposal activities, if necessary, to prevent, to the extent possible, disturbance of the prevailing hydrologic balance. At a minimum, total dissolved solids or specific conductance corrected to 25°C, pH, acidity, alkalinity, total iron, total manganese, sulfates and water levels shall be monitored and reported to the Department at least every 3 months for each monitoring location.

 (c)  The Department may require the operator to conduct additional hydrologic tests, including, but not limited to, drilling, infiltration tests, aquifer tests, chemical and mineralogic analyses of overburden and spoil to demonstrate compliance with this section.

 (d)  The Department may require the operator to conduct monitoring and reporting more frequently than every 3 months, and to monitor additional parameters beyond the minimum specified in this section.

Authority

   The provisions of this §  88.305 amended under the Surface Mining Conservation and Reclamation Act (52 P.S. § §  1396.1—1396.19a); The Clean Streams Law (35 P.S. § §  691.1—691.1001); and section 1920-A of The Administrative Code of 1929 (71 P.S. §  510-20).

Source

   The provisions of this §  88.305 adopted December 19, 1980, 10 Pa.B. 4789, effective July 31, 1982, 12 Pa.B. 2382; amended March 30, 1984, 14 Pa.B. 1143, effective August 10, 1985, 15 Pa.B. 2872; amended December 15, 1995, effective December 16, 1995, 25 Pa.B. 5821. Immediately preceding text appears at serial page (199146).

Cross References

   This section cited in 25 Pa. Code §  88.283 (relatinig to sealing of drilled holes: general requirements).



No part of the information on this site may be reproduced for profit or sold for profit.


This material has been drawn directly from the official Pennsylvania Code full text database. Due to the limitations of HTML or differences in display capabilities of different browsers, this version may differ slightly from the official printed version.