Pennsylvania Code & Bulletin
COMMONWEALTH OF PENNSYLVANIA

• No statutes or acts will be found at this website.

The Pennsylvania Code website reflects the Pennsylvania Code changes effective through 54 Pa.B. 5598 (August 31, 2024).

52 Pa. Code § 57.152. Formats.

§ 57.152. Formats.

 In preparing the Annual Resource Planning Report required by this subchapter, each EDC shall use the current forms and schedules specified by the Commission, which shall include the following:

   (1)  ARPR 1—Historical and Forecast Energy Demand.

   (2)  ARPR 2—Historical and Forecast Connected Peak Load.

   (3)  ARPR 3—Historical and Forecast Number of Connected Customers.

   (4)  ARPR 4—Historical and Forecast Peak Load and Energy.

   (5)  ARPR 5—Existing Generating Capability.

   (6)  ARPR 6—Future Generating Capability Installations, Changes and Removals.

   (7)  ARPR 7—Projected Capacity and Demand.

   (8)  ARPR 8—Qualifying Facility and Independent Power Production Facilities.

   (9)  ARPR 9—Scheduled Imports and Exports.

   (10)  ARPR 10—Summary of Demands, Resources and Energy for the Previous Year.

   (11)  ARPR 11—Transmission Line Projection.

   (12)  ARPR 12—Conservation and Loan Management Program Description.

Authority

   The provisions of this §  57.152 amended under the Public Utility Code, 66 Pa.C.S. § §  501, 524, 1501, 1504 and 2809.

Source

   The provisions of this §  57.152 amended February 25, 2000, effective February 26, 2000, 30 Pa.B. 1129. Immediately preceding text appears at serial pages (250669) to (250670).



No part of the information on this site may be reproduced for profit or sold for profit.


This material has been drawn directly from the official Pennsylvania Code full text database. Due to the limitations of HTML or differences in display capabilities of different browsers, this version may differ slightly from the official printed version.