Pennsylvania Code & Bulletin
COMMONWEALTH OF PENNSYLVANIA

• No statutes or acts will be found at this website.

The Pennsylvania Code website reflects the Pennsylvania Code changes effective through 54 Pa.B. 5598 (August 31, 2024).

52 Pa. Code § 69.2101. Statement of scope.

INTERCONNECTION APPLICATION FEES


§ 69.2101. Statement of scope.

 Sections 69.2102—69.2104 provide guidelines to electric distribution companies and customer-generators regarding appropriate fees to be used in filing and processing interconnection applications under section 5 of the Alternative Energy Portfolio Standards Act (73 P.S. §  1648.5) regarding alternative energy and interconnection standards and § §  75.21, 75.22, 75.31—75.40 and 75.51 (relating to interconnection standards; and dispute resolution).

Source

   The provisions of this §  69.2101 adopted April 3, 2009, effective April 4, 2009, 39 Pa.B. 1676.

Cross References

   This section cited in 52 Pa. Code §  69.2102 (relating to statement of purpose); and 52 Pa. Code §  69.2103 (relating to definitions).



No part of the information on this site may be reproduced for profit or sold for profit.


This material has been drawn directly from the official Pennsylvania Code full text database. Due to the limitations of HTML or differences in display capabilities of different browsers, this version may differ slightly from the official printed version.