§ 69.2102. Statement of purpose.
(a) This section and § § 69.2101, 69.2103 and 69.2104 (relating to interconnection application fees) are intended to provide guidance to electric distribution companies and customer-generators seeking to interconnect with an electric distribution companys distribution system under § § 75.21, 75.22, 75.3175.40 and 75.51 (relating to interconnection standards; and dispute resolution). The application fees set forth under these sections are deemed appropriate. An electric distribution company which seeks to impose fees other than those set forth in § 69.2104 (relating to interconnection application fees) is required to file for Commission approval and make an evidentiary showing that deviation from these sections is appropriate.
(b) Electric distribution companies and entities such as industrial parks or residential developers may negotiate different fees for multiple interconnections.
Source The provisions of this § 69.2102 adopted April 3, 2009, effective April 4, 2009, 39 Pa.B. 1676.
Cross References This section cited in 52 Pa. Code § 69.2101 (relating to statement of scope); and 58 Pa. Code § 69.2103 (relating to definitions).
No part of the information on this site may be reproduced for profit or sold for profit.
This material has been drawn directly from the official Pennsylvania Code full text database. Due to the limitations of HTML or differences in display capabilities of different browsers, this version may differ slightly from the official printed version.