52 Pa. Code § 69.2101. Statement of scope.

INTERCONNECTION APPLICATION FEES


§ 69.2101. Statement of scope.

 Sections 69.2102—69.2104 provide guidelines to electric distribution companies and customer-generators regarding appropriate fees to be used in filing and processing interconnection applications under section 5 of the Alternative Energy Portfolio Standards Act (73 P.S. §  1648.5) regarding alternative energy and interconnection standards and § §  75.21, 75.22, 75.31—75.40 and 75.51 (relating to interconnection standards; and dispute resolution).

Source

   The provisions of this §  69.2101 adopted April 3, 2009, effective April 4, 2009, 39 Pa.B. 1676.

Cross References

   This section cited in 52 Pa. Code §  69.2102 (relating to statement of purpose); and 52 Pa. Code §  69.2103 (relating to definitions).