Pennsylvania Code & Bulletin
COMMONWEALTH OF PENNSYLVANIA

• No statutes or acts will be found at this website.

The Pennsylvania Code website reflects the Pennsylvania Code changes effective through 54 Pa.B. 2336 (April 27, 2024).

58 Pa. Code § 57.25. Turbine operation practices.

§ 57.25. Turbine operation practices.

 Hydroelectric units must operate strictly as run-of-the-river operations without peaking or pulsing modes of operation. Run-of-the-river operation prevents undesirable lake level fluctuations and rapid changes in stream flows below the facility and protects boating and fishing recreational interests. Flashboards not exceeding 6 inches in height will not be considered a peaking or pulsing mode of operation; but, when flashboards are placed in use, specified minimum flows must be continuously maintained. Debris removal plans shall be implemented when flashboard installations are breached by high waters, ice or any other influence.



No part of the information on this site may be reproduced for profit or sold for profit.


This material has been drawn directly from the official Pennsylvania Code full text database. Due to the limitations of HTML or differences in display capabilities of different browsers, this version may differ slightly from the official printed version.