§ 457.9. False certification with bid.
If a contractor makes a false certification with regards to § 457.8(a) or (b), or both (relating to certification of classification and capacity), the contractor shall pay to the Department as liquidated damages an amount equal to 5% of the total amount of the bid or the contractor may be disqualified from bidding on future work for 90 days, or both, as deemed appropriate. If the contractor fails to make the payment within 30 days of notification, the contractor shall be disqualified for 1 year. An application for renewal of prequalification will not be considered by the Department until the contractor makes payment. In lieu of the assessment of liquidated damages or disqualification, or both, the Secretary may issue a warning to the contractor making a false certification when the infraction is the first offense of the contractor.
Source The provisions of this § 457.9 adopted September 21, 1973, effective September 22, 1973, 3 Pa.B. 2133; amended November 28, 1980, effective November 29, 1980, 10 Pa.B. 4470; amended April 11, 1997, effective July 1, 1997, 27 Pa.B. 1798. Immediately preceding text appears at serial pages (122941) to (122942).
No part of the information on this site may be reproduced for profit or sold for profit.
This material has been drawn directly from the official Pennsylvania Code full text database. Due to the limitations of HTML or differences in display capabilities of different browsers, this version may differ slightly from the official printed version.