NOTICES
DEPARTMENT OF
ENVIRONMENTAL PROTECTION
Federal Consistency under the Coastal Zone Management Act; Erie-Western Pennsylvania Port Authority McAllister South Dockwall Replacement
[54 Pa.B. 8197]
[Saturday, December 14, 2024]This notice is published under section 306(d)(14) of the Federal Coastal Zone Management Act of 1972 (CZMA) (16 U.S.C. § 1455(d)(14)), regarding public participation in consistency determinations. The Department of Environmental Protection (Department), Coastal Resources Management Program, has received notice that the Erie-Western Pennsylvania Port Authority (applicant) is proposing to replace an existing concrete seawall within the East Canal Basin, which is located in Presque Isle Bay within the City of Erie, Erie County (Project).
The proposed Project will replace a failing concrete seawall along the north side of the East Canal Basin. The East Canal Basin is located on a parcel owned by the applicant. The applicant proposes to replace a portion of the seawall, utilized by the applicant and their contractors, for maintenance and staging of ongoing Erie port activities. The existing seawall will be replaced by a new steel sheet pile seawall in the same general configuration of the existing seawall. The applicant is not proposing any expansion of existing facilities. The applicant is seeking a Federal authorization from the United States Army Corps of Engineers under section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. § 403) and section 404 of the Federal Clean Water Act (CWA) (33 U.S.C. § 1344) to perform this work.
This Project is subject to Department review for Federal consistency because it is an activity requiring a Federal license or permit and will have reasonably foreseeable effects on this Commonwealth's coastal resources or uses.
In accordance with section 307 of the CZMA (16 U.S.C. § 1456) and the National Oceanic and Atmospheric Administration (NOAA) regulations at 15 CFR Part 930, Subpart D (relating to consistency for activities requiring a Federal license or permit), the applicant has certified that the proposed activity will be conducted in a manner consistent with the applicable enforceable policies of Commonwealth's NOAA-approved Coastal Resources Management Program. Interested parties may request a copy of the Federal Consistency Certification from the Department contact listed as follows.
Questions regarding this review should be directed to Matthew Walderon, Federal Consistency Coordinator, at (717) 772-2196 or by e-mail to RA-Fed_Consistency@ pa.gov.
The Department will consider all comments received on or before Monday, January 6, 2025. Commentators are encouraged to submit comments using the Department's online eComment tool at www.ahs.dep.pa.gov/eComment. Written comments can be submitted by e-mail to ecomment@pa.gov or by mail to the Department of Environmental Protection, Policy Office, 400 Market Street, P.O. Box 2063, Harrisburg, PA 17105-2063. Comments, including comments submitted by electronic mail, must include the originator's name and address.
JESSICA SHIRLEY,
Acting Secretary
[Pa.B. Doc. No. 24-1782. Filed for public inspection December 13, 2024, 9:00 a.m.]
No part of the information on this site may be reproduced for profit or sold for profit.This material has been drawn directly from the official Pennsylvania Bulletin full text database. Due to the limitations of HTML or differences in display capabilities of different browsers, this version may differ slightly from the official printed version.